Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies
-
Aldoga Washdown Facilities: Closed until further notice
- Location
- Aldoga Drive, Aldoga
- Description of Works
- Due to possible contamination, the Aldoga Washdown Facilities is closed until further notice.
- Commencing
- 23 October 2024
- More information
-
Alternate washdown facilities are available at Stowe Road, Calliope.
-
Benaraby Landfill - Fire Water Tanks Installation
- Location
- Benaraby Landfill, 48567 Bruce Highway, Benaraby
- Description of Works
-
This project is included in Council’s 2024/25 Capital Works program and will involve installation of water storage tanks for on-site firefighting when/if required at Council’s Benaraby Landfill site.
Works will include civil and earthworks, road and ancillary works, retaining wall construction, tanks, access and piping installation. - Commencing
- 6 August 2024
- Completion
- 20 December 2024
- More information
-
A wildfire event in 2020 impacted Benaraby Landfill and a site assessment was undertaken to provide recommendations for bushfire mitigation action.
Risks were identified with no standpipe on-site and with mains water trickle feed to the landfill.
During the wildfire event emergency service vehicles had to travel to Benaraby to refill during the wildfire.
This project will install two fire water tanks on-site to meet legislative requirements and provide a source of water for emergency services during a wildfire event.
This will assist with response time during fire emergencies, reducing potential risk to the facility and community.
If visiting Benaraby Landfill you may notice increased work activity occurring. Please be mindful of works occurring and follow any signs or directions.
-
Gladstone Waste Transfer Station - temporary closure Wednesday 18 December 2024
- Location
- Gladstone Waste Transfer Station
- Description of Works
- The Gladstone Waste Transfer Station will be closed from 10am Wednesday 18 December 2024 and reopen as per standard hours on Thursday 19 December 2024.
- Commencing
- 10am Wednesday 18 December 2024
- Completion
- 7.30am Thursday 19 December 2024
- More information
-
There will be no impact on any other Waste Facilities.
We appreciate your patience.
Parks scheduled works
Regular maintenance and operational development of Gladstone Region parks, reserves, open spaces and playgrounds is conducted by Council staff throughout the year including all furniture, play equipment, structures and trails.
Information and updates are posted on our Facebook page.
For more information, please contact Council on (07) 4970 0700.
-
Bulburin National Park - temporarily closed due to road closures
- Location
- Bulburin National Park
- Description of Works
- Bulburin National Park is temporarily closed due to Forestry road and Dawes Range road being unsuitable to drive.
- Commencing
- 31 October 2023
- Completion
- 18 December 2024
- More information
-
As a result, the following campgrounds are temporarily closed until further notice:
- Forestry camp
- Range view camp
- Zamia camp
All permits for closed areas are suspended for the duration of the closure. Commercial tour operators and other permit or agreement holders are not permitted to enter closed areas.Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
-
Calliope District Golf Club Irrigation Upgrade and Soil
- Location
- Calliope District Golf Club, Stowe Road, Calliope
- Description of Works
-
Calliope District Golf Club Irrigation Upgrade and Soil Remediation work is scheduled as part of Gladstone Regional Council’s Capital Works program.
This project will be delivered in stages and involves supply, installation and commissioning of a new irrigation system for the existing eighteen (18) hole course, driving range, bowling green and turf nursery.
Work also includes associated soil remediation works to resolve issues and optimise the irrigation system’s performance. This will include, but is not limited to the improvement in drainage, soil condition and re-turfing of areas on the golf club. - Commencing
- 4 May 2024
- Completion
- 27 June 2025
- More information
-
Work will be scheduled, where practical, to allow patrons to continue using the facility, however at times, access restrictions to specific areas of the golf course will apply. If on-site, please be safety conscious and follow signage and directions.
The project will involve upgrade of the Calliope District Golf Club irrigation system and soil remediation, while maintaining access for golf members to about 15 holes while work proceeds.
During these works, overall water supply to the Calliope District Golf Club irrigation systems will be maintained until the new irrigation system becomes operational.
Planned works - key dates
This extensive project is planned to be delivered in 11 stages through until about May 2025.Works forecast, weather permitting:
- Continuation of Stage 5 works - Sep-Oct (Hole 2)
- Hole 1 opened ahead of schedule
- Hole 2 expected to open on 26 November
- Stage 6 - On hold until under boring machine is available
- Stage 7 works - Oct-Nov (Holes 3 & 4)
- Hole 3 Irrigation main and lateral lines
- Hole 3 minor soil remediation
- Hole 4 Irrigation main and lateral lines
- Hole 4 Soil remediation will be completed at a later date to coincide with works on Holes 10 and 11.
What To Expect- Works will occur six days/week from 6am-6pm Monday to Friday and from 6am-3pm on Saturdays.
- Adjustable works program to maximise patrons use of the facility.
- Some vibration, dust and machinery noise associated with work.
- At times, access restrictions to specific areas.
- Please observe signage and directions during works.
Please use this information as a guide only. Works are subject to weather and on-site conditions. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
- Continuation of Stage 5 works - Sep-Oct (Hole 2)
-
Eurimbula and Deepwater National Park - Feral Animal Management - 29 Nov to 28 Feb 2025
- Location
- Eurimbula and Deepwater National Park
- Description of Works
- In conjunction with the nesting and hatching season for marine turtles as well as the arrival of migratory shorebirds, contractors and QPWS staff will be undertaking controlled trapping of the feral fox and pig population within Eurimbula and Deepwater National Park.
- Commencing
- 29 November 2024
- Completion
- 28 February 2025
- More information
-
This work will be carried out for the duration of the nesting period.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Please monitor park alerts on the department's website for updated information.
This alert applies to the following parks:
-
Gladstone Region Coastal Fox Control Program - Protecting our region’s native wildlife
- Location
- Agnes Water - coastal reserves along Springs Road and Captain Cook Drive
- Description of Works
- As part of the program, Council will undertake soft-jaw foothold trapping and thermal shooting.
- Commencing
- Monday, 10 February 2025
- Completion
- Friday, 14 February 2025
- More information
-
These areas will be closed during this period and will be clearly identified by warning signs placed at all entrances. Please pay heed to signage and restrain pets on leash during the control period.
Beaches will remain open during the day.
If your pet becomes trapped, please call Brent Tangey, Senior Natural Environment Officer on 0407 138 768 for assistance to release the pet.
Please be aware, that you may occasionally hear a firearm being safely discharged as part of the targeted control activities.
If you spot a fox or suspected fox den in the program area, please phone (07) 4970 0700 or report it to Council via our online services platform.
More information on the Coastal Fox Program
-
Reedy Creek Paperbark Forest Walk - Temporary closure
- Location
- Reedy Creek Reserver, Agnes Water
- Description of Works
- Bush Heritage Australia has temporarily closed the Paperbark Forest Walk will be closed to public access from Friday, November 24 until further notice.
- Commencing
- Friday, 24 November 2023
- More information
-
Bush Heritage Australia are working on solutions around parking issues and the impacts visitation has on this fragile environment.
-
Turtleway Bridges - Replacement
- Location
- Stirling Park, Boyne Island and Canoe Point, Tannum Sands
- Description of Works
-
Work is scheduled for replacement of two Turtleway pedestrian bridges as part of our Capital Works program.
Removal of the existing structures and installation of new Turtleway footbridges will reduce ongoing maintenance costs and improve longevity of these valuable community assets. - Commencing
- Late January 2025
- Completion
- 30 June 2025
- More information
-
To keep our community safe, full closure of these footbridges will be needed with no pedestrian bridge access from late January 2025 until about the end of June 2025. Pedestrian detours will be required around the work areas.
For cost savings and work efficiencies, the two Turtleway pedestrian bridges will be closed at the same time.
Works will be scheduled consecutively for bridge removal and replacement at the various sites with community and worker safety a priority.
Replacement of these footbridges will involve installation of new structures to provide improved community connectivity for years to come.
Council looks forward to delivering these asset improvement works and appreciates the patience and understanding of the community while these necessary pedestrian bridge replacements are undertaken.
The Turtleway Bridges Replacement project is proudly funded by the Federal Government’s Local Roads and Community Infrastructure (LRCI) Program - Phase 4.
-
Vehicle access restrictions, Joey Lees beach, Curtis Island
- Location
- Curtis Island National Park and Conservation Park
- Description of Works
-
Vehicle access to the Joey Lees beach and lower sections of the headland is no longer permitted.
This closure is necessary to enable rehabilitation of eroded sections of the Joey Lees headland to protect the natural values of the coastal headland communities. - Commencing
- 1 June 2024
- Completion
- 31 May 2025
- More information
-
It is hoped that through the completion of the rehabilitation works the natural integrity of the headland will be reinstated and continue to enhance natural visitor experiences.
A new three-bay car park has been provided on the top of the headland for day visitors. Existing pedestrian access to the beach and lower sections of the headland are maintained.
Please monitor park alerts on the department's website for updated information.
This alert applies to the following park:
-
No planned burns to report.
- More information
# | Name | Size |
---|
Archived public notices
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
Roadworks, conditions and closures
Refer to the RegionWatch website for up to date road conditions and scheduled works. Information and updates are posted on our Facebook page for short term and unscheduled works.
Regular maintenance and operational development of Gladstone Region roads are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
-
Refer to RegionWatch for current road conditions
-
Lowmead Road - Upgrade Work
- Location
- Staged works along Lowmead Road from the Fingerboard Rd-Lowmead Rd intersection to the town of Lowmead
- Description of Works
-
The Lowmead Road Safety and Sealing Upgrade project consists of four stages of road upgrades forecast to be completed on Lowmead Road during this financial year and the next.
Sections of road will be upgraded from the Fingerboard Road-Lowmead Road intersection to the town of Lowmead.
This project will provide an improved, more resilient road with alignment adjustments to offer increased safety for motorists and improved road resilience during wet weather. - Commencing
- 7 August 2023
- Completion
- Financial year 2024/25
-
What’s been happening?
- Stage 1
- Local road users will notice that Stage 1 of the Lowmead Road works was completed in late-2023, using funding from the Queensland Government’s Transport Infrastructure Development Scheme (TIDS). These completed works are within the first two kilometres of Lowmead Road after turning off from Fingerboard Road.
- Stage 2, 3 and 4
- Vegetation clearing to enable road widening and sealing is now complete.
Planned works, site conditions and weather permitting:
- Stage 2
- Stage 2 is approximately a 7km section of road that commences at the Colosseum Creek crossing and continues towards Lowmead. Construction works are on-track to commence in August 2024.
- Stage 3, Stage 4
- Council has appointed a contractor to accelerate road widening, drainage and sealing works in Stages 3 and 4. The contractor will also be constructing a new bridge across Granite Creek on the upstream side of the current causeway.
- Road sealing works are forecast late-2024.
- Minor road realignments on Lowmead Road will occur late-2024, once the new bridge is ready for operation.
- Road conditions to expect until late 2024
- Suburb: Lowmead to Mount Tom
- Street: Lowmead Road from Clarkes Rd to Fingerboard Rd
- What’s happening?
- Road works. Closed. Local traffic only
- Detour for non-local traffic via Gorge Road, Lowmead or Tablelands Road, Berajondo
- Expect delays. Follow signs and directions
More information
- All forecast works in 2024 will occur either on or directly adjacent to the existing road. Traffic controls will be in place, so please observe directions and reduced speed zones at all times.
- Local road users should anticipate a significant increase in site activity from about May to October 2024 when multiple crews (both Council and Contractors) will be working simultaneously across Stages 2, 3 and 4.
- Noise, dust, construction traffic and heavy machinery is expected in the area.
The Lowmead Road Safety and Sealing Upgrade project is being delivered by Council and its Contractors in 2024 and is included in Council’s Capital Works program. This project has secured the support of the Federal Government to widen and seal more than 20km of Lowmead Road in 2024 via the Remote Roads Upgrade Pilot Program (RRUPP). The Granite Creek Bridge project has secured funding from Disaster Recovery Funding Arrangements (DRFA), which joins Commonwealth and State government funding to help communities recover from disasters.
- Stage 1
-
Turkey Beach Road Upgrades
- Location
- Turkey Beach Road, Turkey Beach
- Description of Works
-
Road realignment upgrade and safety improvement works including road widening and road resealing.
Works Area #1 - Between Dyckhoffs Road and Scrubby Creek
Works Area #2 - Between Scrubby Creek and Sandy Creek
During construction works please plan for possible delays, speed reductions and traffic control measures.
Traffic reduced to single lane, as required.
Motorists are urged to drive carefully through the works area and adhere to any reduced speed limits, changed traffic conditions or directions. - Commencing
- Late May 2024
- Completion
- 30 September 2024
-
Turkey Beach Road Safety Improvement works are proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.
-
Jeffery Court - Road Safety Improvements
- Location
- Jeffery Court, Agnes Water
- Description of Works
-
Council is undertaking road safety improvement work along a section of Jeffery Court adjacent to Tom Jeffery Memorial Park, Agnes Water.
Following community feedback and review of this busy traffic area, consideration has been given to public safety, speed limit and improvements to traffic flow to increase safety for our community and visitors to the region.
Work will be completed in stages as part of Council’s 2024/25 Capital Works program to complement later construction of the nearby Agnes Water Beach Visitor Carpark. - Commencing
- 21 October 2024 (Stage 1), 3 February 2025 (Remaining Stage 1 work and Stage 2)
- Completion
- 18 November 2024 (Majority of Stage 1 roadwork), Stage 2 work completion date, to be advised
-
Project update
- Work on-site will pause from 13 December 2024 and is planned to restart from 3 February 2025.
- Majority of Stage 1 roadworks are complete with a portion of remaining works to be delivered early in 2025.
- Over the festive season, Jeffery Court will be open and able to be used for parallel parking.
Planned works forecast
Work is scheduled, site conditions and weather permitting, along the northern side of Jeffery Court (on the road and embankment near the boundary of NRMA Agnes Water Holiday Park and Tom Jeffery Memorial Park):
- Stage 1 (until 13 Dec 2024) - Drainage, road widening, new kerb, asphalt reseal, line-marking and road sign installation within the work area.
- Stage 2 (expected start from 3 Feb 2025) - Installation of mountable kerbing (remaining Stage 1 work). Construction of retaining wall and boardwalk on embankment adjacent to Tom Jeffery Memorial Park.
More information
To make it safer for drivers, pedestrians, community and visitors to the park and beach, when complete, works along this section of Jeffery Court will introduce:
- Reverse angle parking: 18 parking bays to replace existing parallel parking bays, utilising available space and providing greater off-road safety during vehicle unpacking/loading.
- Lower speed limit: a 10km/hr shared zone will apply.
- No queue signage: traffic will not be permitted to queue on the road.
- Existing one-way traffic flow to remain: current one-way flow of traffic conditions will continue.
- Retaining wall and boardwalk: Work in 2025 to provide a safe pedestrian path to connect to existing pathways.
What to expect during works
During works, you’ll notice workers and activity in the work area with some brief traffic disruption and partial road closure required at times.- Works - Monday to Friday, 7am-5pm, site conditions and weather permitting.
- Traffic management.
- At times, dust and machinery/equipment noise can be expected from the project site.
- Some local traffic only restrictions under traffic control.
- Reduced speed limit.
- At times, partial road closure and road changes.
- Please follow signs and directions.
-
Pittsbay Crescent - New Footpath
- Location
- Pittsbay Crescent, Boyne Island
- Description of Works
-
This project has received Queensland Government funding through Transport and Main Roads’ School Transport Infrastructure Program (STIP) to improve infrastructure and provide greater safety near the drop off/pick-up area of Boyne Island State School.
Work will be delivered by Council’s road crew and is included in Council’s 2024/25 Capital Works program. - Commencing
- 17 September, 2024
- Completion
- 31 December, 2024
-
A SafeST investigation was undertaken in the area by Transport and Main Roads to determine the infrastructure improvements required to improve safety for students.
Work involves installation of a new ramp and footpath connecting the top of the Pittsbay Crescent gate ramp to the left side road reserve of Pittsbay Crescent. Approximately 70m of new footpath has been constructed south of the school towards Beltana Drive to link to existing path within Malpas Park.
This project supports Council’s Pedestrian and Cycle Strategy, providing cyclists and pedestrians with a safe and dedicated pathway, reducing the need to share the roadway with motorists.
Planned work
Footpath work has finished. Handrails for the ramp area near the school are being procured and installation will then follow.
The overall project is expected to be completed about late December.
During works
- Works between Monday to Friday, 7am-5pm.
- Noise, vibration and dust can be expected from the project site.
- At times, some pedestrian and traffic disruptions.
- Please follow signs and directions.
The Boyne Island State School Pittsbay Crescent Footpath project is proudly supported by the Queensland Government’s School Transport Infrastructure Program (STIP) and Gladstone Regional Council.
Water & Sewer interruptions
Refer to the RegionWatch website for up to date interruptions and scheduled works.
Regular maintenance and operational development of Gladstone Region water and sewer networks are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
After water is turned on:
- On resumption of the water supply a hot water tap should be turned on to flush any air pockets from the pipes, then turn the hot water heater on again.
- We advise that you check the water prior to use. If it appears discoloured we suggest you turn on the nearest external tap to the meter and let it run for a period of time, or until it runs clear, and then do the same to the furthest external tap from the meter, to clear your pipework.
- Please do not wash clothes at this time to prevent staining from any discoloured water.
Council apologises for any inconvenience this interruption may cause. For more information contact us online or call on (07) 4970 0700.
-
Unplanned Maintenance - Agnes Water Waste Water Treatment Plant
- Location
- Agnes Water
- Description of Works
- Due to maintenance work at the Trade Waste/Septage receival station at Agnes Water WWTP. All liquid waste disposal at this location is directed to Gladstone Waste Water Treatment Plant, 17 Albert Road, Callemondah.
- Commencing
- Friday 26 July, 2024
-
Water meter readings
- Description of Works
- Gladstone Regional Council (GRC) advises that its next period of half-yearly water meter readings will commence on Monday 11 November 2024.
- Commencing
- 11 November 2024
- Completion
- mid-December 2024
- More information
-
Council staff conducting readings will be dressed in GRC-branded clothing and will carry an authorised officer card featuring photographic identification.
Residents are asked to keep water meters accessible and clear of building materials, soil, vehicles, or other objects.
Council also reminds residents to keep unrestrained dogs controlled and gates closed.
Water consumption for this half-year period will be billed in the half-yearly consumption notice to be issued in February 2025.
Residents unable to locate their water meter can phone Council on 4970 0700.
More information
-
Sewer Manhole Renewal - Gladstone
- Location
- Various locations in Gladstone
- Description of Works
-
Included in Council’s 2023/24 Capital Works program, Sewer Manhole Renewal work is being delivered in stages across Gladstone and involves rehabilitation works to improve reliability of the sewer network, reduce ongoing maintenance costs and meet wastewater sustainability objectives.
Machinery operation, vehicle movements, lighting, odour and noise can be associated with this work. - Commencing
- December 2023
- Completion
- June 2025
- More information
-
The Gladstone Sewer Manhole Renewal project is proudly funded by the Queensland Government’s Works for Queensland funding 2021-24 in association with Gladstone Regional Council.
-
Seventeen Seventy Sewer Rising Main Replacement
- Location
- Captain Cook Drive, Seventeen Seventy
- Description of Works
-
Works to relocate and replace 1000m of existing sewer rising main along the coastline adjacent to Captain Cook Drive at Seventeen Seventy will occur from early December 2024 to June 2025, site conditions and weather permitting.
New alignment of the sewer rising main will prevent risks of uncontrolled sewer release to the immediate environment, supporting objectives of Council’s Our Coast Our Future Coastal Hazard Adaption Strategy to ensure appropriate adaptation responses to help avoid, mitigate, and manage the risk of coastal hazards.
This project is included in Council’s Capital Works program. - Commencing
- Late November 2024
- Completion
- June 2025
- More information
-
Work will generally involve:
- Removal and/or grouting capping of existing redundant sewer rising main (located within the foreshore area),
- Installation of new sewer rising main within the road reserve,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Planned works forecast
- 2 to 11 Dec: Contractors on-site mobilisation
- 12 to 20 Dec: Work on sewage pump station generator replacement
- From 20 Dec: Stop for Christmas period
- 14 Jan 2025: Recommence works on-site
- Works in January: Start of sewer rising main realignment works within the road corridor to be undertaken section-by-section
Work will start in the sewage pump station area for the duration of the December period of works. This work will have minimal impact on the roadway during this time.
What to expect
Work is being planned in stages with public safety as a priority and with consideration of peak holiday times, the community and visitors to our region.
Works will stop over Christmas (from 20 Dec) and recommence in mid-January (14 Jan).
When works are underway in 2025:
- Contractors in the area on weekdays with at times, work at night and on weekends.
- Equipment and machinery operating with noise and dust likely from the project area.
- At times, some pedestrian detours, disruption to traffic flow, single lane alternating traffic and parking restrictions within the work area.
- At times, some amenities near the immediate work area will be closed for public safety.
- Please follow signs and directions and plan for road and pedestrian changes near the works area.
The Seventeen Seventy Sewer Rising Main Replacement project is funded by the Queensland Government’s QCoast2100 program and Gladstone Regional Council.
-
Tannum Sands Sewer Rising Main Replacement
- Location
- Millennium Esplanade, Tannum Sands from the northern end to just south of the Surf Lifesaving Club
- Description of Works
-
Works to upgrade the sewer rising main are anticipated to start in late January 2025, site conditions and weather permitting.
The existing 370m long sewer rising main pipeline, constructed in 1976, is located along the eastern side of Millennium Esplanade, Tannum Sands.
This asset has been condition assessed and identified as being at the end of its service-life and needing replacement. This project is included in Council’s 2024/25 Capital Works program with work to be carried out by a Contractor.
- Commencing
- Late January 2025
- Completion
- June 2025
- More information
-
Work will involve:
- Removal and/or grouting of existing redundant sewer rising main (located under road and footpaths in some areas),
- Installation of new sewer rising main,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Work is being planned with public safety as a priority, with Council extremely mindful of peak holiday times in Tannum Sands with the community, visitors to our region and dates of known community events on Millennium Esplanade considered.
When works start you can expect to see Contractors in the area on weekdays with some work at night and on weekends.
Due to equipment and machinery operating in the area, noise and dust are likely from the project area.
A temporary on-site work area will be established at the northern end of Millennium Esplanade.
The sewer rising main construction involves open trench excavation using temporary fencing and metal plates to protect exposed areas outside of work hours.
At times, some pedestrian detours, disruption to traffic flow, and parking restrictions will be experienced along the esplanade.
Work is planned to occur in stages to help minimise public disruptions.
To keep the public safe, there may be times when some amenities near the immediate work area may also need to be closed.
Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies
Latest CONNECT News out now
More InformationHave your say to help us improve the way we support the Gladstone Region small business community.
Take the surveyThe cookbook is a collaborative effort between Gladstone Regional Council and Gladstone Region Neighbourhood Centre, proudly presented as part of Welcoming Week celebrations.
Download the cookbookGladstone Regional Council
Connect. Innovate. Diversify.
Get in Touch
Phone
(07) 4970 0700
Opening Hours
8.30am - 5pm Monday to Friday
Social media
Postal Address
PO Box 29, Gladstone Qld 4680
Council Offices
101 Goondoon Street, Gladstone Qld 4680
3 Don Cameron Drive, Calliope Qld 4680
41 Blomfield Street, Miriam Vale Qld 4677
Cnr Wyndham & Hayes Avenues, Boyne Island Qld 4680
Rural Transaction Centres
71 Springs Road, Agnes Water Qld 4677
47 Raglan Street, Mount Larcom Qld 4695
Footer Acknowledgement
Gladstone Regional Council would like to acknowledge the Bailai, the Gurang, the Gooreng Gooreng and the Taribelang Bunda people who are the traditional custodians of this land. Gladstone Regional Council would also like to pay respect to Elders both past, present and emerging, and extend that respect to other Aboriginal and Torres Strait Islander people. Learn more about Council's Reconciliation Action Plan (RAP).
Chat Popup
All content © Gladstone Regional Council. All Rights Reserved.
Back to the top