Living Here
- Pets and Animals
- Residents
- Report
- Environment
- Community Development
- Community Investment
- Services
- Emergencies
-
Baffle Creek SES Shed Extension - 2 April 2024 to 30 June 2024
- Location
- 575 Coast Road, Baffle Creek
- Description of Works
-
Council has received funding support for this project through a State Government grant tailored to assist building upgrades for SES groups.
Included in Council’s 2023/24 Capital Works program, these shed extension works will enable a permanent solution for storage of material, supplies and the Baffle Creek SES flood boat.
The shed upgrade will offer easy access to facilities, provide increased floor space for group training, and provide a lockable area for the flood boat, tools and equipment. - Commencing
- 2 April 2024
- Completion
- 30 June 2024
- More information
-
Works will include supply and installation of the shed extension to tie into the existing SES shed, removal and disposal of the existing shipping container, relocation of existing gas bottle, external lighting and stormwater pipes, provision for additional power points and shelving, and installation of internal double lockable doors.
During works:
- Works between Monday to Friday, 6.30am-6.30pm.
- Construction noise from tools and equipment.
- Increased traffic in the area temporarily during construction works.
The Extension of Baffle Creek SES Facility project is funded by the State Government’s SES Support Grant and Gladstone Regional Council.
-
Boyne Tannum Memorial Parklands - Tea House closed for ongoing works
- Location
- Boyne Tannum Memorial Parklands, Pioneer Drive, Boyne Island
- Description of Works
-
The Tea House facility is unavailable for hire due to ongoing works.
- Commencing
- September 2022
- More information
-
Gladstone Aquatic Centre, Gladstone
- Location
- 60 Tank Street, Gladstone
- Description of Works
-
Works in 2021 included installation of site boundary fencing, filtration plant upgrades, Aquatic Play Park upgrades, Building Renewals included amenity upgrades and addition of a new Accessible Adult Change Room and external pool lights replacement.
Works also included Stage 1 Building Renewals, with upgrades to amenities in the 25m pool area and Stage 2 Building Renewals including upgrade to facilities and main amenities building. This included improved change rooms with two new Disability Discrimination Act (DDA) accessible facilities and three new family change rooms.
Works in 2022 have included new roof structures over main amenities, new awning to the existing kiosk and front entrance upgrade. Stage 3 Building Renewals including 25m pool upgrades, building enclosure works and upgrades to the 25m pool water heating system were completed with work then on the 50m grandstand and shade sail upgrades.
- Commencing
- August 2020, various stages
- Completion
- Various stages continuing until 2023
- More information
-
Aquatic Play Park upgrade is complete with towering dumping buckets, water cannons and two slides, offering 13 interactive features for aquatic play.
The Aquatic Play Park operates in the warmer months of the year. Check opening times and learn more about the Gladstone Aquatic Centre and other facilities in the region www.gladstone.qld.gov.au/pools-aquatic-centres
WHAT’S BEEN HAPPENING?
We’re pleased to have introduced our 50m grandstand and shade sail upgrades late last year, providing a fresh, new look to the 50m pool area, and helping to provide all-year-round comfort for our patrons.
25M POOL FILTER UNDERGROUND PIPE REPAIRS
Investigations are continuing into engineering requirements for repairs to the 25m pool filter plant’s underground pipework. Location of the pipe leaks and pipe arrangement could potentially make this work challenging. Planning is underway on how to execute these works safely and with minimal impact on infrastructure.
50M POOL RELINING DEFERRED
Works for complete replacement of pool tiles in the 50m pool, which was planned for Winter 2023 have been deferred.
A new implementation schedule for the 50m pool retiling is being determined.
The new timeframe for these works will be shared when confirmed.
Gladstone Regional Council is being assisted to deliver this improved facility for the region with:
- $2.4m State Government funding, through the 2021-24 Works for Queensland Program,
- $1.2m State Government funding, through the COVID Works for Queensland Program, and
- $1.6m through the Federal Government’s Local Roads and Community Infrastructure Program.
-
Gladstone Transfer Station weighbridge under maintenance
- Location
- Gladstone Transfer Station
- Description of Works
-
Commercial waste is unable to be accepted at the Gladstone Transfer Station today while the weighbridge is being maintained.
During this time, commercial waste customers are to attend the Benaraby Landfill. - Commencing
- Tuesday 23 April 2024
- More information
-
All waste that requires weighing as per Council's Fees and Charges are required to attend the Benaraby Landfill during the maintenance period.
Commercial green waste and scrap metal will continue to be accepted at Gladstone Transfer Station.
There will be no impact on residential users.
We apologise for any inconvenience, and appreciate your patience and understanding.
See Also Transfer Stations and Landfills
-
Miriam Vale Community Centre Upgrade
- Location
- 41 Blomfield St, Miriam Vale
- Description of Works
-
The Miriam Vale Community Centre upgrade will allow for modernisation of the facility which has been used as a place of refuge through multiple disasters including the 2018 Deepwater bushfires and 2019 Mount Maria bushfires.
The upgrade aims to deliver a fit-for-purpose centre that will provide temporary shelter away from the area of impact for people in need.
The upgrade will also play a vital role in creating the social fabric of the region, providing a space that can be used all year round to come together, connect and be involved.
The centre will have a heating, ventilation and air conditioning system (HVAC) installed, electrical upgrade and amenities upgrade with Disability Discrimination Act (DDA) compliance works to help future-proof the facility and provide a comfortable place for residents to seek shelter in the event of an emergency.
- Commencing
- 6 December 2023
- Completion
- 30 June 2024
- More information
-
- Works between Monday to Friday, 7am-5pm, and Saturday, 7am-4.30pm.
- Heavy machinery operating.
- Noise, vibration and dust can be expected from the project site.
This project is proudly funded by the Federal Government’s Black Summer Bushfire Recovery Grants Program and Gladstone Regional Council.
Parks scheduled works
Regular maintenance and operational development of Gladstone Region parks, reserves, open spaces and playgrounds is conducted by Council staff throughout the year including all furniture, play equipment, structures and trails.
Information and updates are posted on our Facebook page.
For more information, please contact Council on (07) 4970 0700.
-
Apex Park - Renew/Replace Retaining Wall
- Location
- Apex Park, Gladstone
- Description of Works
-
As part of Council’s 2023/24 Capital Works program, contractors will construct a new, three-tier retaining wall to replace the existing earth retaining wall structure at Apex Park, Gladstone.
Works will include: demolition of existing retaining wall, excavation and civil works, install of sandstone retaining walls, install of concrete sleeper retaining walls, drainage works, upgrade of existing toilet block
(provisional item), landscaping and remediation work.
Work is planned to start on 13 February, with an expected completion date of 5 June 2024, site conditions and weather permitting.
- Commencing
- 13 February 2024
- Completion
- 5 June 2024
- More information
-
Planned works
7 May to 17 June: Amenities at Apex Park will be closed to enable maintenance to upgrade the facility while retaining wall and landscaping works occur nearby.
During this closure, nearest public amenities are located:
- Reg Tanna Park, Glenlyon Street
- Public toilets to the side of the Council building, 101 Goondoon St, street level
What to expect
- No weekend work.
- Noise from machinery operating.
- At times, some road disruptions/lane closure.
- Traffic control for nearby traffic and pedestrians.
- Some on-street parking restrictions.
The Apex Park Renew/Replace Retaining Wall project is proudly funded by the Federal Government’s Local Roads and Community Infrastructure (LRCI) Program - Phase 3 and Gladstone Regional Council.
-
BITS Golf Club Irrigation Upgrade and Soil Remediation
- Location
- BITS Golf Club, Jacaranda Drive, Boyne Island
- Description of Works
-
BITS Golf Club Irrigation and Soil Remediation work is scheduled as part of Gladstone Regional Council’s 2023/24 Capital Works program.
This project will be delivered in five stages and involves supply, installation, and commissioning of a new irrigation system for the existing thirteen (13) hole course.
Work also includes associated soil remediation works to resolve issues of excess soil and turf in areas on the golf course. - Commencing
- 10 July 2023
- Completion
- 30 April 2024
- More information
-
Work will be scheduled, where practical, to allow patrons to continue using the facility, however at times, access restrictions to specific areas of the golf course will apply.
The project will involve upgrade of the BITS Golf Club irrigation system and soil remediation, while maintaining the existing system and access for golf members to 9 holes. Disruptions will affect about three holes at any one time.
During these works, overall water supply to the BITS Sports Fields irrigation systems will be maintained.
What’s been happening?
- During March, good progress was made on the fifth and final stage of works.
- Irrigation installation is now complete.
- Top dressing of the Fairways is complete.
Planned works
- Work planned, site conditions and weather permitting:
- Minor remediation works.
- Minor remediation works.
Practical completion date of the overall project has been extended to the end of the month.
This extra time will allow additional time for ground recovery and repairs and enable the course to be more durable to sustain golf traffic.
We value the co-operation of members and players and appreciate your patience and understanding during these project works.
- Please refrain from golf cart use on newly turfed and/or disrupted areas.
- Golf cart users are requested to avoid driving over/or in close proximity to sprinkler heads and valve boxes or along irrigation trenching.
- Please remain safety conscious with minor remediation works occurring around the course.
Please use this information as a guide only. Works are subject to weather and on-site conditions. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
-
Bulburin National Park - temporarily closed due to road closures
- Location
- Bulburin National Park
- Description of Works
- Bulburin National Park is temporarily closed due to Forestry road and Dawes Range road being unsuitable to drive.
- Commencing
- 31 October 2023
- Completion
- 2 May 2024
- More information
-
As a result, the following campgrounds are temporarily closed until further notice:
- Forestry camp
- Range view camp
- Zamia camp
All permits for closed areas are suspended for the duration of the closure. Commercial tour operators and other permit or agreement holders are not permitted to enter closed areas.Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
-
Calliope District Golf Club Irrigation Upgrade and Soil
- Location
- Calliope District Golf Club, Stowe Road, Calliope
- Description of Works
-
Calliope District Golf Club Irrigation Upgrade and Soil Remediation work is scheduled as part of Gladstone Regional Council’s Capital Works program.
This project will be delivered in stages and involves supply, installation and commissioning of a new irrigation system for the existing eighteen (18) hole course, driving range, bowling green and turf nursery.
Work also includes associated soil remediation works to resolve issues and optimise the irrigation system’s performance. This will include, but is not limited to the improvement in drainage, soil condition and re-turfing of areas on the golf club. - Commencing
- 4 May 2024
- Completion
- 27 June 2025
- More information
-
Work will be scheduled, where practical, to allow patrons to continue using the facility, however at times, access restrictions to specific areas of the golf course will apply. If on-site, please be safety conscious and follow signage and directions.
The project will involve upgrade of the Calliope District Golf Club irrigation system and soil remediation, while maintaining access for golf members to about 15 holes while work proceeds.
During these works, overall water supply to the Calliope District Golf Club irrigation systems will be maintained until the new irrigation system becomes operational.
Planned works - key dates- Works forecast, weather permitting:
- From 25 April 2024 - Mobilisation on-site
- Saturday, 4 May, 2024 - Anticipated start of works
- Mid-May to late July 2024 - Electrical works
- Early Aug 2024 to late June 2025 - Irrigation installation
- From mid-May 2024 - Anticipated start of irrigation installation
- Late July 2024 to early June 2025 - Soil Remediation
- 27 June 2025 - Anticipated completion
What To Expect
- Works will occur six days/week from 6am-6pm Monday to Friday and from 6am-3pm on Saturdays.
- Adjustable works program to maximise patrons use of the facility.
- Some vibration, dust and machinery noise associated with work.
- At times, access restrictions to specific areas.
- Please observe signage and directions during works.
Please use this information as a guide only. Works are subject to weather and on-site conditions. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
-
Eurimbula and Deepwater National Park - Feral Animal Management
- Location
- Eurimbula and Deepwater National Parks
- Description of Works
-
Fox and Pig Control Work
In conjunction with the nesting season for both migratory shorebirds and marine turtles, QPWS staff will be undertaking controlled baiting of the feral fox and pig population within Eurimbula National Park. This work will be carried out for the duration of the nesting period. - Commencing
- 6 October 2023
- Completion
- 30 April 2024
- More information
-
Please monitor park alerts on the department's website for updated information.
This alert applies to the following parks:
-
Flat Rock Picnic Grounds - Amenities work
- Location
- Flat Rock Picnic Grounds, Rules Beach
- Description of Works
-
Contractors will undertake building and painting works on the amenities located at Flat Rock Picnic Grounds, Rules Beach.
Work is scheduled from 15 April to 3 May, weather permitting and will include pressure cleaning of the building, roof and handrail repairs, water tank replacement and painting.
Temporary fencing will be in place around the immediate work area. Access will remain available to the playground and the remainder of Flat Rock Picnic Grounds and the boat ramp.
Portable toilets will be on-site during works. - Commencing
- 15 April 2024
- Completion
- 3 May 2024
- More information
-
If in the area, please be mindful of works occurring, and follow signage and directions.
These works are included in Council’s 2023/24 Capital Works program.
These Flat Rock Picnic Grounds works are funded by the Queensland Government Department of Agriculture and Fisheries’ Fishing Infrastructure Grants Program and Gladstone Regional Council.
-
Koowin Park - Viewing Platform Upgrade
- Location
- Koowin Park, Kirkwood
- Description of Works
-
Contractors will upgrade the viewing platform at Koowin Park, Kirkwood from 16 April to 10 May, site conditions and weather permitting.
Work has been scheduled to occur after the Easter school holiday period and will involve removal of decking boards, joists and bearers, preparation and installation of new support posts, floor joists and decking boards, and handrail.
Temporary fencing will be in place around the immediate work area. Access will remain available to the playground and the remainder of Koowin Park. - Commencing
- 16 April 2024
- Completion
- 10 May 2024
- More information
-
Work will be carried out from Monday to Friday from 6.30am to 5pm.
At times, there may be noise and dust from the work site.
If in the area, please be mindful of works occurring, and follow signage and directions.
These works are part of Capital Parks Infrastructure works included in Council’s 2023/24 Capital Works program.
-
Kroombit Tops National Park - Razorback track closed
- Location
- Kroombit Tops National Park
- Description of Works
- Razorback track is closed to all traffic from the Razorback camping area to the park boundary on the Biloela side, due serious erosion and track damage.
- Commencing
- 3 October 2023
- Completion
- 30 April 2024
- More information
-
The track will remain closed until repair work can be completed.
Access to the Razorback camping area remains open.
Observe all signage, barriers, and directions from rangers, and do not enter closed areas.
Due to the changed conditions, the visitor experience may be affected.
Please monitor park alerts on the department's website for updated information.
This alert applies to the following park:
-
Pest management control program in Kroombit Tops National Park
- Location
- Kroombit Tops National Park
- Description of Works
- QPWS will be conducting a pest control program from 13/05/2024 through to 26/05/24 within Kroombit Tops National Park.
- Commencing
- 13 May 2024
- Completion
- 26 May 2024
- More information
-
All control activities are conducted in accordance with an approved pest management activity plan that identifies and protects the biodiversity of native species and the safety of visitors to Kroombit Tops National Park
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Facilities will reopen when the event is completed.
Please monitor park alerts on the department's website for updated information.
-
Reedy Creek Paperbark Forest Walk - Temporary closure
- Location
- Reedy Creek Reserver, Agnes Water
- Description of Works
- Bush Heritage Australia has temporarily closed the Paperbark Forest Walk will be closed to public access from Friday, November 24 until further notice while works are undertaken.
- Commencing
- Friday, 24 November 2023
- More information
-
Temporary closure of Joey Lees camp area, Curtis Island
- Location
- Curtis Island National Park and Conservation Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned upgrade works at Joey Lees campground, Curtis Island National Park from 13/5/2024 to 24/05/2024 (weather permitting).
- Commencing
- 13 May 2024
- Completion
- 24 May 2024
- More information
-
Joey Lee's camp area will be closed for the duration of the upgrade works program as specified.
Please monitor park alerts on the department's website for updated information.
Facilities will reopen when construction is completed.
This alert applies to the following park:
-
QPWS Planned Burn in Eurimbula National Park - 15 April - 15 May 2024
- Location
- Eurimbula National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting a planned burns (weather permitting) from 15 April 2024 to 15 May 2024, as part of the fire management program for Eurimbula National Park.
- Commencing
- 15 April 2024
- Completion
- 15 May 2024
- More information
-
Firefighters and machinery may be working along roadsides in the vicinity of the Tanti track and Rodds penninsula camping area. For your safety and the safety of firefighters, please slow down and observe all directions and signs.
Smoke may be seen in the vicinity of Eurimbula campgrounds, Turkey Beach and Captain Creek. Persons with respiratory or other health problems should seek medical advice on mitigating the effects of smoke inhalation.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire and Emergency Services (QFES).
-
Planned Burn - Philip Street Communities and Families Precinct
- Location
- Area behind Philip Street Communities and Families Precinct.
- Description of Works
-
We invite the community to a planned cultural burn workshop to be held at Philip Street Communities and Families Precinct.
The burn will be conducted by Council’s First Nations Fire and Land Officer, Michael Wilmott in the presence of First Nations community members.
The planned burn will be conducted pending favourable weather conditions. - Commencing
- 7am Wednesday 8 May 2024
- More information
-
A smoke warning is in place for residents in nearby areas. We suggest closing your windows and doors and keeping medication close by if you suffer from respiratory conditions.
# | Name | Size |
---|
Archived public notices
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
Roadworks, conditions and closures
Refer to the RegionWatch website for up to date road conditions and scheduled works. Information and updates are posted on our Facebook page for short term and unscheduled works.
Regular maintenance and operational development of Gladstone Region roads are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
-
Refer to RegionWatch for current road conditions
- More information
-
Hampton Drive - New Footpath Construction
- Location
- Hampton Drive (Langdon St-Garnet Rd), Tannum Sands
- Description of Works
-
Work has involved construction of a new 560m long x 2m wide concrete footpath along one side of Hampton Drive.
This project is included in Council’s 2023/24 Capital Works program, and supports Council’s Pedestrian and Cycle Strategy, providing cyclists and pedestrians with a safe and dedicated pathway, reducing the need to share the roadway with motorists. - Commencing
- 15 August 2023
- Completion
- 19 May 2024
- More information
-
To complete this footpath project, upcoming work will involve installation of a raised priority crossing section at the Latrobe St/Hampton Dr intersection to provide greater pedestrian connectivity for the community and improve pedestrian safety in the area.
Planned works
Latrobe St/Hampton Dr intersection
Temporary part road closure, traffic changes and detours:
- Friday 26 and Saturday 27 April: Works, including minor earthworks, construction of new crossing, installation of signage and line-marking.
To keep our community and workers safe, temporary part road closure of a section of Latrobe St (between the Hampton Dr and Madigan Rd intersections) will be necessary. Some local traffic only access restrictions will apply with detours for general traffic around the work site.
What to expect
- Works between Friday and Saturday, 6am-6pm.
- Noise and vibration can be expected from the project site.
- Some traffic disruptions including detours.
- Temporary part road closure of Latrobe Street near the Hampton Drive intersection.
- Detours around the immediate work area.
- Local traffic only access for Latrobe St residents within the immediate work area - access and exit Latrobe St near the Madigan Rd intersection.
- Traffic management at all times.
- More traffic may be experienced on streets along the detour routes.
- Please plan for delays, changed road conditions and detours.
The Hampton Drive, Langdon St to Garnet St, Construct Shared Path project is proudly supported by the Queensland Government’s Cycle Network Local Government Grants Program 2022-2023.
-
Lowmead Road - Upgrade Work
- Location
- Staged works along Lowmead Road from the Fingerboard Rd-Lowmead Rd intersection to the town of Lowmead
- Description of Works
-
The Lowmead Road Safety and Sealing Upgrade project consists of four stages of road upgrades forecast to be completed on Lowmead Road during this financial year and the next.
Sections of road will be upgraded from the Fingerboard Road-Lowmead Road intersection to the town of Lowmead.
This project will provide an improved, more resilient road with alignment adjustments to offer increased safety for motorists and improved road resilience during wet weather. - Commencing
- 7 August 2023
- Completion
- Financial year 2024/25
- More information
-
What’s been happening?
- Stage 1:
- Local road users will notice that Stage 1 of the Lowmead Road works was completed in late-2023, using funding from the Queensland Government’s Transport Infrastructure Development Scheme (TIDS). These completed works are within the first two kilometres of Lowmead Road after turning off from Fingerboard Road.
- Stage 4
- Vegetation clearing is expected to be completed in Stage 4 (between Granite Creek and the sealed section of road closest to Lowmead) before Easter.
Planned works, site conditions and weather permitting:
- Stage 2, Stage 3, Stage 4:
- Stage 2 vegetation clearing will commence mid-April. This is approximately a 7km section of road that commences at the Colosseum Creek crossing and continues towards Lowmead. Council has also mobilised a small internal road crew to commence road construction in Stage 2.
- Council will mobilise a civil contractor to site in May to accelerate road widening, drainage and sealing works in Stages 3 and 4. This contractor team will supplement a Council road crew who is already working within Stage 3.
- Construction works will not be occurring over the Easter holiday period.
More information
- All forecast works in 2024 will occur either on or directly adjacent to the existing road. Traffic controls will be in place, so please observe directions and reduced speed zones at all times.
- Local road users should anticipate a significant increase in site activity from about May to October 2024 when multiple crews (both Council and Contractors) will be working simultaneously across Stages 2, 3 and 4.
- In preparation for Stage 3 and 4 works, vegetation clearing is necessary to enable the road to be widened.
- A fauna spotter will be on-site during clearing works.
- Noise, dust, construction traffic and heavy machinery is expected in the area.
- Council takes a sensitive approach to vegetation clearing and has completed environmental assessments of the area with the necessary permits and approvals required.
- Mulched material will be transported to Council depots, used in Council parks and community spaces and offered to interested community groups for use. (More information will be provided when available).
The overall Lowmead Road Safety and Sealing Upgrade project is included in Council’s Capital Works program and has secured the support of the Federal Government to widen and seal more than 20km of Lowmead Road in 2024 via the Remote Roads Upgrade Pilot Program (RRUPP)
- Stage 1:
-
Glenlyon St (Bramston-Herbert St) - Road Upgrade
- Location
- Glenlyon St (Bramston-Herbert St) - Road Upgrade
- Description of Works
-
This project involves significant road renewal and widening along Glenlyon Street, both north and south bound lanes, footpath work including property access and crossings, kerb and channel replacement, removal and installation of road signs and landscape works within the median strip. Relining to upgrade and improve stormwater pipes was carried out first.
Work includes road profiling which involves removal of the existing layers of the road pavement material, enabling new road pavement material and then a new asphalt seal to be placed for north and southbound lanes along Glenlyon St (Bramston St-Herbert St). During these works, the area of road being worked on will close to traffic, with detours required. - Commencing
- 5 February 2024 (Road and footpath upgrade work starts)
- Completion
- 30 June 2024, site conditions and weather permitting
- More information
-
This work will improve asset performance and longevity, reducing ongoing maintenance costs for road infrastructure in this area.
Stormwater pipe and sewer relining works were carried out in March 2023.
Completing this work first will enable road and footpath upgrade to follow to lessen the project’s overall disruption and impacts for residents and the community.
Road and footpath upgrades will involve extensive upgrade work to our road infrastructure and at times, may involve lane/road closures, pedestrian disruptions and significant traffic changes.
Planned work forecast
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
- February to March: Stage 1 - Glenlyon St, southbound - footpath works.
- Late March to May: Stage 2 - North and Southbound Central Lanes - median strip works.
- May to July: Stage 3 - North and Southbound Outside Lanes - road works.
- June to Late July: Stage 4 - Asphalt and line-marking works all areas - final road works and line marking.
Tuesday, 26 March to late May 2024
Traffic reduced to one-lane travelling north and south along Glenlyon St (between Bramston St and Herbert St) with closure of lanes nearest the median.
This will enable widening works on the central median island, northbound and southbound lane road reconstruction and reconstruction of the centre median.
At times, on-street parking bays along this section of Glenlyon Street will be closed during works.
Please follow signs and directions, plan for delays, road changes and detours.
What to expect
Work will be carried out Monday to Fridays, with weekend work expected at varying times throughout the construction, where approved by Council, to mitigate interruptions to traffic flow and impacts to the community.
- Noise, vibration, dust and operation of heavy machinery can be expected from the project site.
- Motorists are urged to follow signage and directions of traffic control including any detours.
- Pedestrians please follow signage and directions.
- Please plan for delays, prepare for changed road conditions and detours.
The Glenlyon St (Bramston-Herbert St) Road Upgrade project is funded by the Queensland Government’s Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.
Water & Sewer interruptions
Refer to the RegionWatch website for up to date interruptions and scheduled works.
Regular maintenance and operational development of Gladstone Region water and sewer networks are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
After water is turned on:
- On resumption of the water supply a hot water tap should be turned on to flush any air pockets from the pipes, then turn the hot water heater on again.
- We advise that you check the water prior to use. If it appears discoloured we suggest you turn on the nearest external tap to the meter and let it run for a period of time, or until it runs clear, and then do the same to the furthest external tap from the meter, to clear your pipework.
- Please do not wash clothes at this time to prevent staining from any discoloured water.
Council apologises for any inconvenience this interruption may cause. For more information contact us online or call on (07) 4970 0700.
-
Seventeen Seventy Sewer Rising Main Replacement
- Location
- Captain Cook Drive, Seventeen Seventy
- Description of Works
-
Works to relocate and replace 1000m of existing sewer rising main along the coastline adjacent to Captain Cook Drive at Seventeen Seventy will occur from about March to September 2024, pending availability of materials and contractors, site conditions and weather permitting.
New alignment of the sewer rising main will prevent risks of uncontrolled sewer release to the immediate environment, supporting objectives of Council’s Our Coast Our Future Coastal Hazard Adaption Strategy to ensure appropriate adaptation responses to help avoid, mitigate, and manage the risk of coastal hazards.
This project is included in Council’s Capital Works program. - Commencing
- 1 March 2024
- Completion
- 30 September 2024
- More information
-
Work will involve:
- Removal and/or grouting of existing redundant sewer rising main (located under road and footpaths in some areas),
- Installation of new sewer rising main,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Work is being planned with public safety as a priority, with Council extremely mindful of peak holiday times in Agnes Water and Seventeen Seventy with the community, visitors to our region and dates of known community events considered.When works start in 2024 you can expect to see Contractors in the area on weekdays with some work at night and on weekends.
Due to equipment and machinery operating in the area, noise and dust are likely from the project area.
The sewer rising main construction involves open trench excavation using temporary fencing and other protection measures to safeguard exposed areas outside of work hours.
At times, some pedestrian detours, disruption to traffic flow, and parking restrictions will be experienced within the work area.
Work is planned to occur in stages to help minimise public disruptions.
To keep the public safe, there may be times when some amenities near the immediate work area may also need to be closed.
-
Silverdale Reservoir Renewal - Calliope
- Location
- Mingara Crescent, Calliope
- Description of Works
-
• Council proposes to renew the Silverdale Reservoir which is a critical infrastructure asset with a capacity of 2.2ML.
• The reservoir supplies potable water to 403 properties in the township of Calliope, supplying drinking water to residential, community and business assets within the Silverdale Reservoir Catchment. - Commencing
- 8 January 2024
- Completion
- 10 May 2024
- More information
-
Works will include:
- Construction of a set of aluminium stairs and landings to access the top of the reservoir safely
- Strengthening the existing aluminium columns supporting the reservoir roof with a proprietary system
- Lightning protection
- Replace scour grate and overflow pipeline
- Security measures (for example fencing and locking systems)
- Measures to increase the integrity of the reservoir such as wall sealing, concrete and joint repairs
- Replace isolation and control valves and internal pipework
The Silverdale Reservoir Renewal project is proudly funded by the Queensland Government’s Building our Regions program.
-
Tannum Sands Sewer Rising Main Replacement
- Location
- Millennium Esplanade, Tannum Sands from the northern end to just south of the Surf Lifesaving Club
- Description of Works
-
Works to upgrade the sewer rising main will occur from about March to August 2024, site conditions and weather permitting.
The existing 370m long sewer rising main pipeline, constructed in 1976, is located along the eastern side of Millennium Esplanade, Tannum Sands.
This asset has been condition assessed and identified as being at the end of its service-life and needing replacement. This project is included in Council’s 2023/24 Capital Works program with work to be carried out by a Contractor.
- Commencing
- March 2024
- Completion
- August 2024
- More information
-
Work will involve:
- Removal and/or grouting of existing redundant sewer rising main (located under road and footpaths in some areas),
- Installation of new sewer rising main,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Work is being planned with public safety as a priority, with Council extremely mindful of peak holiday times in Tannum Sands with the community, visitors to our region and dates of known community events on Millennium Esplanade considered.
When works start in 2024 you can expect to see Contractors in the area on weekdays with some work at night and on weekends.
Due to equipment and machinery operating in the area, noise and dust are likely from the project area.
A temporary on-site work area will be established at the northern end of Millennium Esplanade.
The sewer rising main construction involves open trench excavation using temporary fencing and metal plates to protect exposed areas outside of work hours.
At times, some pedestrian detours, disruption to traffic flow, and parking restrictions will be experienced along the esplanade.
Work is planned to occur in stages to help minimise public disruptions.
To keep the public safe, there may be times when some amenities near the immediate work area may also need to be closed.
-
Advanced Water Meter Infrastructure - Beecher and Burua
- Location
- Properties in Beecher and Burua
- Description of Works
-
Every property in Beecher and Burua with an existing constant flow scheme/trickle feed connection (including access only connections) will have advanced water metre infrastructure installed between March and June 2024.
These upgrades form Stage 2 of a multi-year Capital Works project across the Gladstone Region.
Work will be carried out between 7am and 5pm Monday to Friday, with weekend work (involving later start times) approved by Council.
The new advanced water meter infrastructure will be installed in two phases to about 542 properties.
Beecher and Burua residents are advised of temporary interruptions to water supply in their neighbourhood throughout this project.
- Commencing
- 1 March 2024
- Completion
- 30 June 2024
- More information
-
- Council’s Water Operations staff and contractor will carry identification with them.
- Phase 1 of the installation will take up to 1.5 hours with Phase 2 taking approximately 10-15 mins, depending on the site difficulty.
- A vacuum truck may be required at some sites. If this is the case, please expect some noise.
- Water will be disconnected during works, stopping water flow to your tanks for the installation period.
- Once alterations at your property are complete, Council will leave a calling card in your letterbox.
- Following installation, residents can then sign up to the My Water portal which will show near real-time water usage. Users can set up high usage alerts and receive monthly water usage reports by email.
Find out more general information about Stage 2 works, Advanced Waters Meters, and Frequently Asked Questions online.
-
Smoke Testing of Sewer Network
- Location
- Gladstone, Boyne Island, Tannum Sands, and Agnes Water/Seventeen Seventy
- Description of Works
-
Council will begin smoke testing as part of source detection investigations within the sewerage networks of Gladstone, Boyne Island, Tannum Sands, and Agnes Water/Seventeen Seventy from Monday 7 August, 2023. Testing works are expected to continue through until approximately the end of June 2024.
This work is being done to ensure Council continues to deliver safe and reliable sewerage services across the Gladstone Region. Inspections of the network will be carried out by our experienced contractor, Detection Services. - Commencing
- Monday 7 August, 2023
- Completion
- End of June 2024
- More information
-
How testing is done
- A machine will be used to blow smoke into the sewer pipes to identify infrastructure defects (smoke testing).
- Sewerage infrastructure and outdoor connections to the network will be inspected.
- Photographs of sewerage infrastructure and outdoor connections to the network may be taken as part of the investigations.
- Your sewerage services will not be interrupted during this time.
What to expect- Smoke testing will take place between 7am and 5pm, Monday to Saturday, and 8am and 4pm on Sundays, weather permitting.
- The contractor will only require access to external areas of your property, including your back yard. Please contact Alex Miller of Detection Services on 0433 963 900 if special access arrangements need to be made due to a security gate or pets.
- There may be small puffs of smoke coming up through sewer maintenance holes in the ground and sewer vents, which are usually located on the roof of your property.
- The presence of smoke inside your residence can be an indicator of faulty plumbing. Please seek assistance from the investigation team if you see any smoke coming from your wastewater system (i.e. toilet and drains).
- Smoke testing is a well-established procedure used by water utilities for many years. The smoke is non-toxic, non-flammable and safe for people and pets.
- Every effort will be made to minimise inconvenience during works.
Council requests residents briefly run taps and flush toilets prior to smoke testing to ensure traps in drainage pipework are filled with water. This will reduce the likelihood of smoke infiltration into the premises during testing.
Entry to properties will be made in accordance with Part 2, Section 144 of Local Government Act 2009 and for the purpose of monitoring compliance in accordance with Chapter 5, Part 2, Section 410 of Water Supply (Safety and Reliability) Act 2008. Authorised officers will carry and produce, upon request, Council issued photo ID and will advise of their entry at the time. If no one is at home, advice of entry will be left on the property with contact details for any queries or enquiries.
Council would appreciate your cooperation in ensuring clear access is available to any sewer manholes situated on your property during this time.
Living Here
- Pets and Animals
- Residents
- Report
- Environment
- Community Development
- Community Investment
- Services
- Emergencies
Latest CONNECT News out now
More InformationGladstone Regional Council
Connect. Innovate. Diversify.
Get in Touch
Phone
(07) 4970 0700
Opening Hours
8.30am - 5pm Monday to Friday
Social media
Postal Address
PO Box 29, Gladstone Qld 4680
Council Offices
101 Goondoon Street, Gladstone Qld 4680
3 Don Cameron Drive, Calliope Qld 4680
41 Blomfield Street, Miriam Vale Qld 4677
Cnr Wyndham & Hayes Avenues, Boyne Island Qld 4680
Rural Transaction Centres
71 Springs Road, Agnes Water Qld 4677
47 Raglan Street, Mount Larcom Qld 4695
Footer Acknowledgement
Gladstone Regional Council would like to acknowledge the Bailai, the Gurang, the Gooreng Gooreng and the Taribelang Bunda people who are the traditional custodians of this land. Gladstone Regional Council would also like to pay respect to Elders both past, present and emerging, and extend that respect to other Aboriginal and Torres Strait Islander people. Learn more about Council's Reconciliation Action Plan (RAP).
Chat Popup
All content © Gladstone Regional Council. All Rights Reserved.
Back to the top