Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies
-
Gladstone Aquatic Centre - 50m pool maintenance closure
- Location
- Gladstone Aquatic Centre, Tank Street, Gladstone
- Description of Works
-
While the weather’s a little cooler, the 50m pool will temporarily close for maintenance from Monday, 28 July.
Work will include pool drainage to enable minor tile repair and cleaning, as well as filtration system cleaning.
Site investigation works will also occur in preparation for extensive works later to retile the 50m pool, a project included in Council’s 2025/26 Capital Works program. - Commencing
- Monday, 28 July 2025
- Completion
- Monday, 11 August 2025
- More information
-
What to expect:
- Activity in the area
- Temporary fencing in place
- Please follow signs and directions
During this temporary closure, please use the 25m indoor, heated pool. If you require assistance for special access to the 25m pool, please enquire at the check-in desk at the Gladstone Aquatic Centre entrance.
The 50m pool is expected to reopen to patrons on Monday 11 August.
We appreciate your patience and understanding while works occur.
Check opening times and learn more about the Gladstone Aquatic Centre and other facilities in the region www.gladstone.qld.gov.au/pools-aquatic-centres.
Parks scheduled works
Regular maintenance and operational development of Gladstone Region parks, reserves, open spaces and playgrounds is conducted by Council staff throughout the year including all furniture, play equipment, structures and trails.
Information and updates are posted on our Facebook page.
For more information, please contact Council on (07) 4970 0700.
-
Agnes Water Skate Park Revitalisation
- Location
- Springs Road, Agnes Water
- Description of Works
-
Funded under Round 1 of the Australian Government’s Growing Regions Program, the $1.94M Agnes Water Skate Park Revitalisation project is progressing and is in the detailed design and statutory government approval stage.
The detailed design for the project is based on the concept design which was endorsed by Council and developed through extensive consultation with the community and stakeholders.
Construction commencement will be dependent on completion of the detailed design and receival of any required statutory government approvals.
At this stage, the timeline for construction is anticipated to commence during the 2025/26 financial year.
- Commencing
- Thursday 9 January 2025, Site Investigation and Detailed Design phase
- Completion
- 17 November 2025, Detailed Design and Statutory Government Approval Stage
- More information
-
Once complete, Agnes Water will have a fit for purpose skate facility that is safe, modern and suits a range of skill levels for skateboards, BMX and scooters.
More updates on this exciting upgrade will be shared when the project moves closer to construction.
The $1.94M Agnes Water Skate Park Revitalisation project has been jointly funded by the Australian Government’s Growing Regions Program - Round 1 and Gladstone Regional Council.
Project dates mentioned are a guide only. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
* To enable our teams to focus on project progression, for project queries please contact Council on 4970 0700.
-
Bulburin National Park - Range View Camp temporarily closed
- Location
- Bulburin National Park
- Description of Works
- Range View campground is temporarily closed due to the access 4WD loop road being unsuitable to drive.
- Commencing
- 19 December 2024
- Completion
- 2 September 2025
- More information
-
As a result, the following campgrounds are temporarily closed until further notice:
- Range view camping area
- 4WD Loop road
All permits for closed areas are suspended for the duration of the closure. Commercial tour operators and other permit or agreement holders are not permitted to enter closed areas.Zamia and Old Forestry camping areas are currently open. These can be accessed via Bulburin Forestry road and Dawes Range Road.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
-
Canoe Point Parklands – May-October 2025
- Location
- Canoe Point, Tannum Sands
- Description of Works
- The boardwalk in the Canoe Point Parklands is temporarily closed for maintenance inspections. Other maintenance works will also occur, including painting the amenities block.
- Commencing
- Wednesday, 28 May 2025
- Completion
- Friday, 31 October 2025
- More information
-
Please observe signage in the parklands while these maintenance works are underway.
We appreciate the community’s patience and understanding while the maintenance is carried out.
More information on Canoe Point Parklands
-
Eurimbula National Park - Reduced campsites due to erosion
- Location
- Eurimbula National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) have advised that the northern section of Eurimbula Creek campground has been affected by erosion due to high tides and creek mouth dynamics over the past several years.
- Commencing
- 19 June 2025
- Completion
- 31 January 2026
- More information
-
As a result, 3 camp sites on the northern end of the campground are closed to allow rehabilitation to take place.
Please do not enter this area to allow sand replenishment and revegetation to occur.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers, and directions from rangers and do not enter closed areas.
-
Footpath closure due to tree maintenance works - Wyndham Park, Boyne Island
- Location
- Footpath between Wyndham Park and the access to Alkina Crescent
- Description of Works
- The footpath will be closed to all pedestrians, cyclists, and other users for the duration of the maintenance.
- Commencing
- Monday 4 August 2025
- Completion
- Wednesday 6 August 2025
- More information
-
The tree maintenance works are being undertaken to ensure public safety.
What to expect
Please be mindful when using the footpath through this location.
- Works Monday to Friday, 7.30am-4pm, weather permitting.
- Please follow directions and signage in the area.
-
Police Creek Railway Bridge Closure
- Location
- Near Blain Park, off Cemetery Road, Gladstone
- Description of Works
- Site investigations carried out as part of planning for future remedial works on the Police Creek Railway Bridge, located near Blain Park in Gladstone, have found the bridge to be structurally unsound.
- Commencing
- Thursday, 24 July 2025
- More information
-
As a result, the bridge is closed to all pedestrian access effective immediately.
Signage will be installed as soon as possible to communicate this closure to the public clearly.
The community’s safety is our highest priority.
We thank you for your understanding and co-operation as we work to address these issues.
Project works are included in Council’s 2025/26 Capital Works program
-
QLD Government Planned construction works - closure to visitor facilities
- Location
- Joseph Banks Conservation Park
- Description of Works
-
This is a Queensland Government Department of the Environment, Tourism, Science and Innovation project.
Joseph Banks Conservation Park will be undergoing construction and maintenance as part of an interpretive capital works project working with Traditional Owners groups Gooreng Gooreng, Gurang, Taribelang Bunda and Bailai. - Commencing
- 4 March 2025
- Completion
- 30 November 2025
- More information
-
Throughout this period, the following areas will be closed to the public:
- the headland carpark at the end of Sir Raphael Cilento Drive
- the Round Hill headland tracks
- the Wave and Bustard Bay lookouts
- the Round Hill Creek track section from Endevour St junction to the headland carpark
The following areas will remain open to the public:- Maritime memorial walk and carpark
- The Round Hill Creek track from the Cook Monument to Endeavour St junction
As part of additional works commencing on 11/06/25, a section of the Round Hill Creek Track will undergo an upgrade. As a result, there will be no access to the beach via the eastern section of the Round Hill Creek track. This work is expected to be completed by the 10/08/25.
Alternative access to the beach can be found via the Captain Cook monument.
The Queensland Government thanks you for your patience while they improve the park facilities for you and other park visitors.
Facilities will reopen when construction is completed.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
This alert applies to the following park:
Please visit the QLD Government Parks and Forests website for more information.
-
Reedy Creek Paperbark Forest Walk - Temporary closure
- Location
- Reedy Creek Reserver, Agnes Water
- Description of Works
- Bush Heritage Australia has temporarily closed the Paperbark Forest Walk will be closed to public access from Friday, November 24 until further notice.
- Commencing
- Friday, 24 November 2023
- More information
-
Bush Heritage Australia are working on solutions around parking issues and the impacts visitation has on this fragile environment.
-
Temporary Small Dogs and Puppies Area in Webb Park, Gladstone
- Location
- Small Dogs and Puppies Area in Webb Park, Gladstone
- Description of Works
- Council has temporarily closed the Small Dogs and Puppies area in Webb Park (a dog off-leash park) on Palm Drive as we undertake maintenance work to rectify dangerous ground conditions.
- Commencing
- Friday 11 April 2025
- Completion
- August 2025
- More information
-
A temporary small dog park has been created within the larger dog park to provide a safe space for those who need one. It is accessible through the main gate and turn to the right, and through the new gate. The bigger dogs can continue straight through to the other park.
We appreciate your patience and cooperation while works are undertaken.
If you have any questions about these works, please contact Council on 4970 0700.
See also
-
QPWS Planned Burn Castle Tower National Park - 22 April - 31 August 2025
- Location
- Castle Tower National Park
- Description of Works
- The Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Castle Tower National Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Castle Tower NP. Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn Eurimbula National Park - 22 April - 31 August 2025
- Location
- Eurimbula National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Eurimbula National Park from 22 of April 2025 - August 31 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Eurimbula NP, including campgrounds and day-use areas, and within the townships of Agnes Water, Captain Creek and Turkey Beach.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn for Kroombit Tops National Park - 14 July 2025 and the 31 July 2025
- Location
- Kroombit Tops National Park
- Description of Works
-
Queensland Parks and Wildlife Service QPWS) will be conducting planned burns between 14th July 2025 and the 31st August 2025, as part of the annual hazard reduction and conservation management program for parks and forests.
These burns are being undertaken to help protect life and property in the event of a wildfire. - Commencing
- 14 July 2025
- Completion
- 31 August 2025
- More information
-
Smoke may be seen in the vicinity of Tableland Road. Persons with respiratory or other health problems should seek medical advice on mitigating the effects of smoke inhalation.
During the planned burns, these areas may be temporaily closed or restricted to public access:
- Tableland Road
- WW2 Bomber site
- The Wall Day Use Area
Observe all signage, barriers and directions from rangers, and do not enter closed areas.
All permits for closed areas are suspended for the duration of the closure. To apply for a refund or camping credit, contact the online booking service at qpws@des.qld.gov.au.
Commercial tour operators and other permit or agreement holders are not permitted to enter closed areas.
Check Park Alerts regularly for updates on current park conditions.
Refunds can be applied for via your online account at qld.gov.au/camping.
For your safety, please proceed with caution along all park access roads.
Facilities will reopen when conditions are considered safe.
This alert applies to the following park:
-
QPWS Planned Burn Deepwater National Park - 22 April - 31 August 2025
- Location
- Deepwater National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Deepwater National Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Deepwater NP, including campgrounds and day-use areas, and within the townships of Agnes Water and Deepwater.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn in Joseph Banks Conservation Park - 22 April - 31 August 2025
- Location
- Joseph Banks Conservation Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Joseph Banks Conservation Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Joseph Banks Conservation Park, including lookouts and walking tracks, and within Seventeen Seventy.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
# | Name | Size |
---|
Archived public notices
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
Roadworks, conditions and closures
Refer to the RegionWatch website for up to date road conditions and scheduled works. Information and updates are posted on our Facebook page for short term and unscheduled works.
Regular maintenance and operational development of Gladstone Region roads are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
-
Refer to RegionWatch for current road conditions
-
Agnes Water Beach Visitor Carpark
- Location
- Agnes Street, Agnes Water
- Description of Works
-
Work to construct an overflow carpark at 5 Agnes Street, Agnes Water, to provide an additional 49 car parking bays to one of the region’s most popular beaches.
The project will provide safer and more convenient access to Main Beach, help to ease road congestion in the area, and better care for the surrounding environment. - Commencing
- 23 June 2025
- Completion
- August 2025
-
More Information
- 49 car parking bays, including two PWD (People with Disabilities) parking bays for increased accessibility.
- A limited carpark footprint to minimise the impact on the surrounding environment.
- Stormwater and environmental management processes to better manage the site and the surrounding environment.
- A 6:1 ratio of parking spaces to trees to utilise natural shading options.
- Boom gate entrance and secured boundary to prevent after-hours use (i.e. Illegal camping)
- Acoustic wall to reduce noise impact on neighbouring properties with an environmentally considerate design to maintain the existing tree along the boundary.
- Public seating and a water fountain for community use.
- Potential locations for public art installations both inside and outside the car park.
- Ecology and engineering issues highlighted in the court decision are being adhered to.
- On-street RV (recreational vehicle) parking along Agnes Street.
Works update
Following site mobilisation, erosion and sediment control measures were promptly installed to protect surrounding environmental values.
Construction is progressing well with key early works completed on site.
Set out and surveying activities were completed early in the program to guide construction and ensure accuracy in stormwater infrastructure and pavement levels.
Recent inclement weather and the high ground water is causing challenges and delays.
Progress to date:
- Construction of the sub-base with imported fill 60% complete
- Stormwater pits concrete bases complete
- Progressed the installation of the stormwater system progressed to 60%
Further updates will be provided as the works continue to progress.
What to expect during works
During works, you’ll notice workers and activity in the work area with some brief traffic disruption and partial road closure required at times.
- Works will take place Monday to Saturday, 6.30am-5pm, site conditions and weather permitting.
- At times, dust and machinery/equipment noise can be expected from project site.
- Some local traffic-only restrictions under traffic control.
- Reduced speed limit.
- At times, partial road closure and road changes.
- Please follow signs and directions.
Date references indicated are a guide only. Due to the nature of construction projects and unforeseen delays, works/dates may vary.
The Agnes Water Beach Visitor Carpark is proudly supported by the Queensland Government’s Department of Transport and Main Roads and Gladstone Regional Council.
-
Dalga Rd, Builyan - Culvert Renewal
- Location
- Dalga Road, Builyan
- Description of Works
-
Culvert renewal works are planned to start in August with construction expected to take about eight to 16 weeks, site conditions and weather permitting. A temporary side-track will be in place around these works.
This project is included in our 2025/26 Capital Works program and will be delivered by Council’s road crew. - Commencing
- 1 August 2025
- Completion
- 30 November 2025
-
The existing culvert has been identified for replacement, with this project aiming to provide a safer culvert structure, future-protecting this asset against erosion and environmental damage and reducing the frequency of future maintenance.
What to expect
Please be mindful when driving through this location that there will soon be work crews and heavy machinery on site.
When the single lane side-track is established, detour signage and traffic control will be installed while culvert renewal works are carried out.
No disruptions to property access is expected.
- Works Monday to Friday, 7am-5pm, weather permitting.
- Noise, vibration and dust from the work area is expected.
- Heavy machinery and equipment operating.
- Traffic management at times, including traffic disruptions and delays.
- Please follow directions and signage in the area.
The Dalga Road Culvert Renewal project is proudly supported by Transport Infrastructure Development Scheme (TIDS) 2025/26 funding and Gladstone Regional Council.Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
-
End of Parksville Drive to Kahler Close - New Footpath
- Location
- Parksville Drive to Kahler Close, Kirkwood
- Description of Works
-
Work to construct a new footpath connecting the end of Parksville Drive to Kahler Close, Kirkwood is anticipated to start in about July.
This project will involve construction of about 80m of new pathway and is included in Council’s 2024/25 Capital Works program.
In the lead up to footpath construction, surveys have been underway in the area and site preparations will start soon. - Commencing
- 1 July 2025
- Completion
- 31 August 2025
-
The new pathway will connect to existing footpath in the area, provide greater pedestrian connectivity for the community and improve pedestrian safety to the Kirkwood shopping centre.
This project supports Council’s Pedestrian and Cycle Strategy, providing cyclists and pedestrians with a safe and dedicated pathway, reducing the need to share the roadway with motorists.
Planned Works
Site preparation works will start soon.- Two trees on the footpath alignment have been condition assessed and identified for removal in coming weeks.
- Council takes a sensitive approach to remove trees only where absolutely necessary to enable works and to ensure the safety of workers and community.
- More trees will be planted as part of landscape works towards completion of footpath construction.
- Overall path construction works: Anticipated to start from about July for about six weeks, weather permitting.
- In March: Targeted tree removal, electrical works including installation of electrical conduit, light pole footings.
- From about July: Construction of new footpath, installation of kerb ramps, bollards, signage.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
To keep our community safe and to minimise disruptions:- Work will occur in stages, commencing with tree removal in the next two weeks followed by the electrical works, weather permitting.
- Works will take place Monday to Friday, 6am-6pm.
- Machinery noise, vibration and dust can be expected from the project site.
- At times, some pedestrian and traffic disruptions.
- Please follow signs and directions.
The end of Parksville Drive to Kahler Close Construct Shared Path project is proudly supported by the Queensland Government’s Cycle Network Local Government Grants Program and Gladstone Regional Council.
-
Jeffery Court - Road Safety Improvements
- Location
- Jeffery Court, Agnes Water
- Description of Works
-
Council is undertaking road safety improvement work along a section of Jeffery Court adjacent to Tom Jeffery Memorial Park, Agnes Water.
Following community feedback and review of this busy traffic area, consideration has been given to public safety, speed limit and improvements to traffic flow to increase safety for our community and visitors to the region.
Work will be completed in stages as part of Council’s 2024/25 Capital Works program to complement later construction of the nearby Agnes Water Beach Visitor Carpark. - Commencing
- 21 October 2024 (Stage 1). Further work dates for Stage 1 completion and Stage 2 works to be advised.
- Completion
- Dates to be advised.
-
Project update
- Majority of Stage 1 roadworks are complete with a portion of remaining works to be delivered.
Work is scheduled, site conditions and weather permitting, along the northern side of Jeffery Court (on the road and embankment near the boundary of NRMA Agnes Water Holiday Park and Tom Jeffery Memorial Park):
- Stage 1 - Drainage, road widening, new kerb, asphalt reseal, line-marking and road sign installation within the work area. Installation of mountable kerbing.
- Stage 2 - Construction of retaining wall and boardwalk on embankment adjacent to Tom Jeffery Memorial Park.
More information
To make it safer for drivers, pedestrians, community and visitors to the park and beach, when complete, works along this section of Jeffery Court will introduce:
- Reverse angle parking: 18 parking bays to replace existing parallel parking bays, utilising available space and providing greater off-road safety during vehicle unpacking/loading.
- Lower speed limit: a 10km/hr shared zone will apply.
- No queue signage: traffic will not be permitted to queue on the road.
- Existing one-way traffic flow to remain: current one-way flow of traffic conditions will continue.
- Retaining wall and boardwalk: Work in 2025 to provide a safe pedestrian path to connect to existing pathways.
What to expect during works
During works, you’ll notice workers and activity in the work area with some brief traffic disruption and partial road closure required at times.- Works - Monday to Friday, 7am-5pm, site conditions and weather permitting.
- Traffic management.
- At times, dust and machinery/equipment noise can be expected from the project site.
- Some local traffic only restrictions under traffic control.
- Reduced speed limit.
- At times, partial road closure and road changes.
- Please follow signs and directions.
-
Lowmead Road - Upgrade Work
- Location
- Staged works along Lowmead Road from the Fingerboard Rd-Lowmead Rd intersection to the town of Lowmead
- Description of Works
-
The Lowmead Road Safety and Sealing Upgrade project consists of four stages of road upgrades forecast to be completed on Lowmead Road during FY24, FY25 and FY26.
Sections of road will be upgraded from the Fingerboard Road-Lowmead Road intersection to the town of Lowmead.
This project will provide an improved, more resilient road with alignment adjustments to offer increased safety for motorists and improved road resilience during wet weather. - Commencing
- 7 August 2023
- Completion
- Financial year 2025/26
-
What’s been happening?
ROAD CUT AT GRANITE CREEK BRIDGE - CLOSED TO ALL TRAFFIC - UNTIL FURTHER NOTICE
UPDATE @ 22 APRIL 2025
- Following significant rainfall and damage to the temporary crossing across Granite Creek in early April 2025, Lowmead Road remains cut at the Granite Creek crossing with a full closure in place to all traffic.
- Site inspections and damage assessments at the site are continuing.
- Road closed barriers are in place with the causeway closed to all traffic. Local access is not permitted.
- The working area that has been developed in Granite Creek to support bridge construction is an active worksite. Public access is not permitted. Please observe all construction signage and barriers that are in place to protect our community from construction site hazards.
- While the road remains closed to all traffic, a diversion around the area is in place. Please continue to drive safely, to conditions, and plan extra time for travel.
- Early inspections indicate that to rebuild the causeway road to a limited condition, capable of withstanding one-way traffic, substantial civil works and time would be required.
- The normal creek flows are too high, and the banks are too steep, to allow for any local access/side track to be considered.
- Our officers are working diligently, various options are currently being outworked and a number of our teams are focussed on delivering the best possible outcome for the community.
- We appreciate your patience and understanding while we work to determine the next steps for our road network in this area.
- Granite Creek Bridge
- Bridge construction works, including minor road adjustments to align road approaches with the new bridge.
- Stages 2, 3 and 4 of Lowmead Road
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
Planned works, site conditions and weather permitting:
- Stage #2
- Stage #2 is approximately a 7km of section of road that commences at Colosseum Creek crossing and continues towards Lowmead. Construction works commenced in August 2024 and were completed in May 2025. This excludes the Gin Creek crossing works, anticipated to occur in July-August. Further updates will be provided noting it is expected that these works will require the full closure of the road for a period of time, noting there are no options for side-tracks/detours around the Gin Creek crossing.
- While project works are underway, Lowmead Road is open to local traffic only, specifically for access to homes and properties. All residents who must use the road are asked to slow down, drive to conditions, observe warning signs and reduced speed zones.
- Stage #3, Stage #4
- Council has a Contractor team working on these sections of road, which are separated by Granite Creek. The Contractor team is also completing the Granite Creek Bridge works.
- Lowmead Road sustained significant damage during a flood event in early April 2025 and is currently closed to the public. The Contractor has established a temporary track for construction purposes only. There is no road access available to the public through Granite Creek.
- Road conditions to expect
- Suburb: Lowmead Road to Mount Tom
- Street: Lowmead Road from Clarkes Road to Fingerboard Road
- What’s happening:
- Road works. Closed. Local traffic only.
- Detour for non-local traffic via Gorge Road, Lowmead Road or Tablelands Road, Berajondo.
- Expect delays. Follow signs and directions.
More information
- All forecast works in 2025 will occur either on or directly adjacent to the existing road. Traffic controls will be in place, so please observe directions and reduced speed zones at all times.
- Local road users should anticipate significant site activity while multiple crews (both Council and Contractors) will be working simultaneously across Stages 2, 3 and 4 and the Granite Creek Bridge site.
- Noise, dust, construction traffic and heavy machinery is expected in the area.
The Lowmead Road Safety and Sealing Upgrade project is being delivered by Council and its Contractors in 2024 and is included in Council’s Capital Works program. This project has secured the support of the Federal Government to widen and seal more than 20km of Lowmead Road in 2024 via the Remote Roads Upgrade Pilot Program (RRUPP). The Granite Creek Bridge project has secured funding from Disaster Recovery Funding Arrangements (DRFA), which joins Commonwealth and State government funding to help communities recover from disasters.
-
Matthew Flinders (Marina) Bridge closure for routine scheduled maintenance - 12 August 2025
- Location
- Matthew Flinders (Marina) Bridge, Bryan Jordan Drive, Gladstone
- Description of Works
- Council wishes to advise that the Matthew Flinders (Marina) Bridge on Bryan Jordan Drive will be closed for planned maintenance.
- Commencing
- 6.30am Tuesday 12 August 2025
- Completion
- 4pm Tuesday 12 August 2025
-
During this period, the bridge will be closed to all vehicles and unavailable for watercraft requiring a bridge lift.
While under traffic management, detours will be in place for all vehicular traffic, and an alternative route will need to be used via Hanson Road & Alf O’Rourke Drive.
We appreciate your patience and understanding while these essential works are carried out.
Please contact Water Mechanical-Electrical Team on 4970 0700 regarding any issues or concerns.
-
Oyster Creek, Round Hill Rd - Roadworks
- Location
- Oyster Creek, Round Hill Road
- Description of Works
-
These works are included in Council’s 2024/25 Capital Works program and will involve widening, sealing, road stabilisation and construction of guardrail/safety barriers across Oyster Creek.
The work zone is 400m either side of Oyster Creek, Round Hill Road, in vicinity of Murphy Road.
There will be traffic disruptions with at times, delays of up to 10 mins experienced to enable road sealing and road stabilisation activities.
To minimise disruptions, where practical, necessary delays during works will be planned with consideration of peak travel times for work and school. - Commencing
- 19 May 2025
- Completion
- 31 August 2025
-
PLANNED WORKS FORECAST
Works are anticipated to occur in the period from 19 May to end August, site conditions and weather permitting.- Road widening, stabilisation and sealing 400m either side of Oyster Creek.
- Installation of concrete batter protection and guardrails.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
WHAT TO EXPECT
Please be mindful of construction works occurring:
- Work will be carried out Monday to Sunday from 6am to 6pm.
- Noise, vibration and dust from the work area is expected.
- Heavy machinery and equipment operating.
- Traffic disruptions and traffic management with at times, delays of up to 10 mins.
- Reduced speed limit.
- Please plan for delays, drive to conditions and follow directions and signage in the area.
The Oyster Creek, Round Hill Road safety improvement works are proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.
-
Road closure due to the Broadacres fire hazard, Yacht Road, Tannum Sands
- Location
- Yacht Road, Tannum Sands
- Description of Works
- Council advises travelling with caution and following all advice from emergency services.
- Commencing
- Monday 4 August 2025
- Completion
- Until safe to re-open
-
For the latest updates on road closures, visit qldtraffic.qld.gov.au and regionwatch.gladstone.qld.gov.au.
-
Rocky Crossing Road - Roadworks
- Location
- Rocky Crossing Road, Round Hill
- Description of Works
- These works are included in Council’s 2024/25 Capital Works program and will involve widening, rehabilitation of the road and resealing. All works will occur on the current road alignment.
- Commencing
- Mid-March 2025
- Completion
- 29 August 2025
-
Planned works
- Majority of project work is complete.
- By end of August: Contractor to demobilise from site
- September: Brief return to site for second-seal layer and line-marking
During works please follow signs and directions in the area.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
The Rocky Crossing Road, Round Hill project is proudly funded by the Australian Government’s Roads to Recovery 2024-25 program.
-
Temporary Closure of Matthew Flinders (Marina) Bridge - Sunday 24 August 2025 (5am-10.30am)
- Location
- Matthew Flinders (Marina) Bridge
- Description of Works
- The bridge will be closed to vehicular traffic for the Gladstone Ports Corporation Port to Park Fun Run.
- Commencing
- 5am Sunday 24 August, 2025
- Completion
- 10.30am Sunday 24 August, 2025
-
Pedestrian traffic will be permitted for the duration of the event.
Thank you for your cooperation and patience while our community enjoys and participates in this fantastic community fundraiser once again.
-
Trudy Avenue, Calliope - Footpath Repairs
- Location
- Trudy Avenue, Calliope
- Description of Works
-
These works are required to replace identified footpath defects.
This project supports Council’s Pedestrian and Cycle Strategy, providing cyclists and pedestrians with a safe and dedicated pathway, reducing the need to share the roadway with motorists. - Commencing
- 24 June 2025
- Completion
- November 2025
-
What to expect
- Works Mon-Fri, 6am to 6pm.
- Footpath will remain operational to pedestrians.
- No traffic delays expected.
- If in the area, please be mindful of workers and follow signs and directions.
Water & Sewer interruptions
Refer to the RegionWatch website for up to date interruptions and scheduled works.
Regular maintenance and operational development of Gladstone Region water and sewer networks are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
After water is turned on:
- On resumption of the water supply a hot water tap should be turned on to flush any air pockets from the pipes, then turn the hot water heater on again.
- We advise that you check the water prior to use. If it appears discoloured we suggest you turn on the nearest external tap to the meter and let it run for a period of time, or until it runs clear, and then do the same to the furthest external tap from the meter, to clear your pipework.
- Please do not wash clothes at this time to prevent staining from any discoloured water.
Council apologises for any inconvenience this interruption may cause. For more information contact us online or call on (07) 4970 0700.
-
Endeavour St, Seventeen Seventy - Stormwater Pipe Repair
- Location
- Endeavour Street, Seventeen Seventy
- Description of Works
- Contractors will undertake repair work on stormwater assets located under Endeavour Street.
- Commencing
- 1 August 2025
- Completion
- 22 August 2025
- More information
-
Investigations have revealed stagnant water, silt and sediment buildup, and breaks and cracks in sections of the existing stormwater pipeline.
Pipework condition and its ability to manage stormwater in the area has been assessed with the pipe location and proximity to the nearby conservation area considered.
The Contractor will remove a section of stormwater pipe and pit and replace with new pipe, stormwater pit and headwall. Works will include site preparation, roadworks, traffic management and road surface re-instatement.
Strict controls will be in place to ensure no disturbance occurs within the nearby Joseph Banks Conservation Park boundary.
Sewer services are not expected to be affected by these renewal works; however, this method of pipeline rehabilitation may produce minor noise disturbances, additional traffic, and possibly odour for short periods.
What to expect- Works between 1 to 22 Aug, 6am-6pm, weather permitting.
- Council Contractors will carry identification.
- Access if required only to external areas of property.
- You will receive further access notification from the Contractor closer to works.
-
Hanson Road - Water Main Replacement
- Location
- Hanson Road (Lord St to Tranberg St), Gladstone
- Description of Works
-
Works will be undertaken by a local, civil contractor, to deliver a critical water infrastructure upgrade along Hanson Road, Gladstone.
This upgrade forms part of Council’s broader asset renewal strategy to improve water service reliability across the region.
The project involves replacement of the existing, aging, asbestos cement water main with a new, modern, high-density polyethylene (HDPE) water main. Additionally, all associated valve assemblies and connections will be replaced to meet current standards and support long-term performance of the water network. - Commencing
- 1 May 2025
- Completion
- End August 2025
- More information
-
The existing water main has reached the end of its service life and is increasingly vulnerable to leaks and failures.
Replacing it with a durable HDPE pipe will:
- Improve water supply security for local businesses and residents,
- Reduce the risk of future unplanned outages,
- Support current and future development in the area.
WHAT TO EXPECT
- Works will take place along Hanson Road, extending from the corner of Lord St to the corner of Tranberg St.
- Works will occur Monday to Saturday, from 6.30am to 5pm.
- Short-term water outages: Advance notice will be provided to impacted properties ahead of planned disruptions.
- Traffic impacts: Temporary traffic management measures will be in place, affecting inbound traffic along Hanson Road heading to the CBD. This may result in limited parking availability and changes to traffic flow during construction hours.
- Noise and dust: Some noise, dust and vibration may occur during excavation and pipe installation, but measures will be taken to minimise inconvenience.
-
Calliope Sewer Pump Station Works
- Location
- Monterey Way, Calliope
- Description of Works
- Works will be undertaken to upgrade the current chemical dosing unit on site to improve corrosion control and reduce sewer odour.
- Commencing
- 13 May 2025
- Completion
- Mid-September 2025
- More information
-
Civil and electrical works will be required to replace the existing temporary unit and install a permanent chemical dosing unit.
This project aims to provide improved infrastructure, reducing the need for on-going maintenance while reducing the risk of unplanned sewer disruptions for residents.
These works are included in Council’s Capital Works program.
Above dates are a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
- Works from Monday to Friday, 7am-4.30pm, weather permitting.
- Machinery operating.
- Concrete slab demolition, removal and construction.
- Noise, vibration, odour and dust can be expected from the project site.
- At times, some additional traffic in the area and pedestrian disruptions.
- No interruption to sewer services is expected.
If near the area, please be mindful of works and follow signs and directions.
-
Sewer Main Renewal
- Location
- Several locations across Gladstone, Boyne Island, Tannum Sands and Calliope
- Description of Works
-
Sewer main renewal works will occur in stages in various locations across the region.
Works are part of a multi-year Capital Works project to renew sewer main assets in areas of Boyne Island, Calliope, Gladstone and Tannum Sands to improve network reliability, operational efficiency and reduce ongoing maintenance costs. - Commencing
- Monday 28 April 2025 (Stage 1)
- Completion
- Friday 10 October 2025 (Stage 1)
- More information
-
This project will involve sewer cleaning, relining and junction sealing.
Sewer services are not expected to be affected by these renewal works however this method of pipeline rehabilitation may produce minor noise disturbances, additional traffic, and possibly odour for short periods.
Access to properties will only be required when entry is necessary to access Council’s sewer main assets, complete the works, or for service junction repair and connection to the new sewer pipe. Entry to properties will be made in accordance with Part 2, Section 144 of Local Government Act 2009.
Planned Works, weather permitting
- 12 May to 24 June: Sewer cleaning works
- 16 June to 10 October: Relining works
- Program of works information will be provided here when finalised.
Above dates are a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.What to expect
- Works between 6.30am to 6.30pm, Monday to Friday and 6.30am to 5pm on Saturday, weather permitting.
- Council Contractors will carry identification.
- Access if required only to external areas of property, including backyards.
- Please ensure clear access to any sewer main access points on your property.
Residents will receive further access notification from the Contractor closer to works. Please relocate/restrain any animals and enable access through any gates during this timeframe.
-
Unplanned Maintenance - Agnes Water Waste Water Treatment Plant
- Location
- Agnes Water
- Description of Works
- Due to maintenance work at the Trade Waste/Septage receival station at Agnes Water WWTP. All liquid waste disposal at this location is directed to Gladstone Waste Water Treatment Plant, 17 Albert Road, Callemondah.
- Commencing
- Friday 26 July, 2024
-
Seventeen Seventy Sewer Rising Main Replacement
- Location
- Captain Cook Drive, Seventeen Seventy
- Description of Works
-
Works to relocate and replace 1000m of existing sewer rising main along the coastline adjacent to Captain Cook Drive at Seventeen Seventy will occur from early December 2024 to June 2025, site conditions and weather permitting.
Works will start near Endeavour Park and finish near the Seventeen Seventy boat ramp.
New alignment of the sewer rising main will prevent risks of uncontrolled sewer release to the immediate environment, supporting objectives of Council’s Our Coast Our Future Coastal Hazard Adaption Strategy to ensure appropriate adaptation responses to help avoid, mitigate, and manage the risk of coastal hazards.
This project is included in Council’s Capital Works program. - Commencing
- Late November 2024
- Completion
- June 2025
- More information
-
Work will generally involve:
- Removal and/or grouting capping of existing redundant sewer rising main (located within the foreshore area),
- Installation of new sewer rising main within the road reserve,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Planned works forecast, site conditions and weather permitting
The project has reached finalisation stage with some rectification work planned.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
The Seventeen Seventy Sewer Rising Main Replacement project is funded by the Queensland Government’s QCoast2100 program and Gladstone Regional Council.
-
Advanced Water Meters - Stage 4 Installation
- Location
- Gladstone Central, Barney Point, Callemondah, Kirkwood, New Auckland, West Gladstone and parts of South Gladstone.
- Description of Works
-
Upgrade of existing water meter infrastructure to new, advanced water meter infrastructure at residential and commercial properties in Gladstone Central, Barney Point, Callemondah, Kirkwood, New Auckland, West Gladstone and parts of South Gladstone.
These works are Stage 4 of a whole-of-region, multi-year Capital Works project to upgrade existing water meter infrastructure to new, advanced water meter infrastructure. - Commencing
- July 2025
- Completion
- Late 2025
- More information
-
The installation of advanced water meters and access to associated technology will provide significant benefits to residential households and businesses by:
- Enabling early detection of leaks.
- Providing data and information online so the user can review and manage their water usage.
- Enabling Council officers to respond more effectively to usage enquiries regarding connections.
Every property in Gladstone Central, Barney Point, Callemondah, Kirkwood, New Auckland, West Gladstone and parts of South Gladstone with an existing water meter will have upgraded infrastructure installed between July and Late 2025, between 7am and 5pm Monday to Friday, with weekend work (involving later start times) approved by Council.
The age of a property’s existing water meter will determine if it is fully replaced as part of the upgrade, or if the existing asset can be retained and an advanced water meter infrastructure sensor added. There is no cost to property owners associated with this upgrade.
What to expect during works
- Council Contractors, Taggle Systems, will carry identification with them.
- Water meter upgrade takes about 15 minutes depending on the complexity of your meter.
- A vacuum truck may be required at some sites. If this is the case, please expect some noise.
- Water will be disconnected during works, stopping water flow for the installation period.
- If water is flowing through the meter and we are unable to make contact, we will come back at a later stage.
- A calling card will be left in your letterbox/on your property to advise if the installation was complete or if you need to contact Council to arrange a time for installation completion.
If you have animals or locked gates and need to be present at the install, or if you have any questions about this project, please contact Council on 4970 0700 or visit your local Council office at Mount Larcom, Calliope or Gladstone.
Following installation, residents can sign up to the My Water portal which will show near real-time water usage. Users can set up high usage alerts and receive monthly water usage reports by email.
The advanced water meter upgrade program supports Council’s commitment to continuously improve focus and practices around smart asset management.
Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies

Latest CONNECT News out now
More Information
The cookbook is a collaborative effort between Gladstone Regional Council and Gladstone Region Neighbourhood Centre, proudly presented as part of Welcoming Week celebrations.
Download the cookbookGladstone Regional Council
Connect. Innovate. Diversify.
Get in Touch
Phone
(07) 4970 0700
Opening Hours
8.30am - 5pm Monday to Friday
Social media
Postal Address
PO Box 29, Gladstone Qld 4680
Council Offices
101 Goondoon Street, Gladstone Qld 4680
3 Don Cameron Drive, Calliope Qld 4680
41 Blomfield Street, Miriam Vale Qld 4677
Cnr Wyndham & Hayes Avenues, Boyne Island Qld 4680
Rural Transaction Centres
71 Springs Road, Agnes Water Qld 4677
47 Raglan Street, Mount Larcom Qld 4695
Footer Acknowledgement
Gladstone Regional Council would like to acknowledge the Bailai, the Gurang, the Gooreng Gooreng and the Taribelang Bunda people who are the traditional custodians of this land. Gladstone Regional Council would also like to pay respect to Elders both past, present and emerging, and extend that respect to other Aboriginal and Torres Strait Islander people. Learn more about Council's Reconciliation Action Plan (RAP).
Chat Popup
All content © Gladstone Regional Council. All Rights Reserved.
Back to the top