Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies
-
Benaraby Landfill - Piggyback Liner System Installation
- Location
- Benaraby Landfill, 48567 Bruce Highway, Benaraby
- Description of Works
-
This project is included in Council’s 2024/25 Capital Works program and is aimed to maximise current landfill airspace capacity.
Works will include relocation of landfill gas infrastructure, civil and earthworks and the installation of a geomembrane liner.
The piggyback liner system will ensure Council meets environmental and legislative requirements, and will enable maximum utilisation of Cell 3a by extending cell airspace. - Commencing
- 3 February 2025
- Completion
- 31 July 2025
- More information
-
The Benaraby Landfill site, activated in 1989 to cater for waste disposal in our region, has been master-planned to facilitate 12 cells.
Cell 1 and Cell 2 are filled and closed, Cell 3a constructed in 2021, is filling fast and approaching the end of its expected five-year life-span.
Capacity forecasts in mid-December 2024 indicated Cell 3a is 45 per cent full. Considering our region’s waste disposal data, Cell 3a is predicted to reach capacity by June 2027.
Cell 3a was designed to be filled to the height of the adjoining Cell 1. A piggyback liner system now needs to be installed between the two cells to prevent potential contamination of ground water and soil and to ensure leachate from waste is captured in the Cell 3a leachate management system.
What to expect
If visiting, or passing by Benaraby Landfill, you may notice increased work activity occurring.
Please be mindful of works occurring, of increased traffic through entry gates and on roads within the facility and follow any signs or directions.
-
Gladstone Aquatic Centre Carpark Upgrade
- Location
- 60 Tank Street, Gladstone
- Description of Works
-
Front entry carpark used for disabled parked and a drop off zone will not be accessible due to undergoing upgrades.
Works carried out are to make the disabled carparks compliant and to freshen up line marking. - Commencing
- Monday 26 May 2025
- Completion
- Friday 30 May 2025
- More information
-
Disabled parking is still available in the main car park.
Parking on the grass is strictly prohibited and patrolled by Local Laws.
What to expect
Traffic control will be in place throughout operating hours to provide escort support to patrons needing to be dropped off or assisted for mobility restrictions.
Please be mindful of work occurring and follow any signs or directions.
We appreciate the community’s patience and understanding while the work is carried out.
- Yellow – remove existing car parking spaces and install 2 PWD spaces to current design standards
- Blue Dots – Bollards will be repositioned to guide pedestrians and create extra room for vehicle access
- Blue shaded area – Will be a hatched out no parking area acting as a traffic island
- Blue dashed line – Give way bar
- Single Blue dot _ Give way sign
- This area will be one way only with 2 PWD parking spaces and available for deliveries, buses, taxies etc.
- A handrail will be placed on the ramp from the top car park to assist with the slope.
-
Gladstone City Library - Concrete Remediation Works
- Location
- Gladstone City Library, 39 Goondoon Street, Gladstone
- Description of Works
-
Concrete remediation works will be undertaken by contractors at the Gladstone City Library.
Works will primarily be in and around the lower-level carpark.
The project will occur in four stages with construction work in one area at a time to leave the remaining carpark open to the public. - Commencing
- 25 March 2025
- Completion
- 4 July 2025 (subject to weather and site conditions)
- More information
-
Barricades will be installed in the work area with pedestrian detours in place.
Access to the stairs, lift and disabled parking will remain open during works.
What to expect:
- Noise from machinery operating
- Changes to pedestrian and carpark access
If in the area, please be mindful of works occurring and follow any signs or directions.
We appreciate the community’s patience and understanding whilst the maintenance is carried out.
-
Shell QGC LNG Plant - notification of flaring activity
- Location
- LNG plant on Curtis Island
- Description of Works
- Shell QGC LNG Plant will undertake maintenance works, and at times during this period, there may be larger than normal flame and smoky flare during the shutdown and ramp-up activities of the maintenance period.
- Commencing
- Friday, 16 May 2025
- Completion
- Tuesday 8 June 2025
- More information
-
If smoky flaring does occur, it will be managed via regular operational conditions and processes, and in accordance with the relevant regulatory requirements. When the maintenance activities are completed, the flare will return to its normal operation.
For more information regarding air quality, view the Queensland Government’s monitoring results for the Gladstone Region at www.ehp.qld.gov.au/air/data/search.
Parks scheduled works
Regular maintenance and operational development of Gladstone Region parks, reserves, open spaces and playgrounds is conducted by Council staff throughout the year including all furniture, play equipment, structures and trails.
Information and updates are posted on our Facebook page.
For more information, please contact Council on (07) 4970 0700.
-
Agnes Water Skate Park Revitalisation
- Location
- Springs Road, Agnes Water
- Description of Works
-
Funded under Round 1 of the Australian Government’s Growing Regions Program, the $1.94M Agnes Water Skate Park Revitalisation project is progressing and is in the detailed design and statutory government approval stage.
The detailed design for the project is based on the concept design which was endorsed by Council and developed through extensive consultation with the community and stakeholders.
Construction commencement will be dependent on completion of the detailed design and receival of any required statutory government approvals.
At this stage, the timeline for construction is anticipated to commence during the 2025/26 financial year.
- Commencing
- Thursday 9 January 2025, Site Investigation and Detailed Design phase
- Completion
- 17 November 2025, Detailed Design and Statutory Government Approval Stage
- More information
-
Once complete, Agnes Water will have a fit for purpose skate facility that is safe, modern and suits a range of skill levels for skateboards, BMX and scooters.
More updates on this exciting upgrade will be shared when the project moves closer to construction.
The $1.94M Agnes Water Skate Park Revitalisation project has been jointly funded by the Australian Government’s Growing Regions Program - Round 1 and Gladstone Regional Council.
Project dates mentioned are a guide only. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
* To enable our teams to focus on project progression, for project queries please contact Council on 4970 0700.
-
Bulburin National Park - Range View Camp and Dawes Range road temporarily closed
- Location
- Bulburin National Park
- Description of Works
- Range View campground and Dawes Range road is temporarily closed due to the road being unsuitable to drive.
- Commencing
- 19 December 2024
- Completion
- 19 June 2025
- More information
-
As a result, the following campgrounds are temporarily closed until further notice:
- Range view camping area
- Dawes Range road
- 4WD Loop road
All permits for closed areas are suspended for the duration of the closure. Commercial tour operators and other permit or agreement holders are not permitted to enter closed areas.Zamia and Old Forestry camping areas are currently open. These can be accessed via Bulburin Forest road.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
-
Calliope District Golf Club Irrigation Upgrade and Soil
- Location
- Calliope District Golf Club, Stowe Road, Calliope
- Description of Works
-
Calliope District Golf Club Irrigation Upgrade and Soil Remediation work is scheduled as part of Gladstone Regional Council’s Capital Works program.
This project will be delivered in stages and involves supply, installation and commissioning of a new irrigation system for the existing eighteen (18) hole course, driving range, bowling green and turf nursery.
Work also includes associated soil remediation works to resolve issues and optimise the irrigation system’s performance. This will include, but is not limited to the improvement in drainage, soil condition and re-turfing of areas on the golf club. - Commencing
- 4 May 2024
- Completion
- 27 June 2025
- More information
-
Work will be scheduled, where practical, to allow patrons to continue using the facility, however at times, access restrictions to specific areas of the golf course will apply. If on-site, please be safety conscious and follow signage and directions.
The project will involve upgrade of the Calliope District Golf Club irrigation system and soil remediation, while maintaining access for golf members to about 15 holes while work proceeds.
During these works, overall water supply to the Calliope District Golf Club irrigation systems will be maintained until the new irrigation system becomes operational.
Planned works - key dates
This extensive project is planned to be delivered in 11 stages through until about June 2025.
Works forecast, weather permitting
Wet weather in April slowed progress and limited access to the course.
Planned work, weather permitting
Works on the course had been progressing well prior to the recent inclement weather. The project has incurred 12 days of inclement weather over the last month slowing progress and limiting access to the course.
- Hole 9 - April-May
- Hole recovery and handover to club
- Hole 12 - May
- Tee remediation works
- Main and lateral irrigation lines installed
- Soil remediation and swale drain works
- Stage 11 (Hole 10 & Hole 11) - May to June
- Soil remediation and returf works
- Irrigation installation
What To Expect- Works will occur six days/week from 6am-6pm Monday to Friday and from 6am-3pm on Saturdays.
- Adjustable works program to maximise patrons use of the facility.
- Some vibration, dust and machinery noise associated with work.
- At times, access restrictions to specific areas.
- Please observe signage and directions during works.
Please use this information as a guide only. Works are subject to weather and on-site conditions. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary.
- Hole 9 - April-May
-
Changes to Capricorn Cay National Park camping bookings for 2026
- Location
- Capricorn Cay National Park
- Description of Works
- QPWS is changing to a ‘Booking Season’ model to book camping permits for the Capricornia Cays in 2026. Camping permits for all Capricornia Cay islands will be released to the public on set days and times advised in advance giving customers ample time and equal opportunity to obtain permits. The first camping permit release for 2026 will be Tuesday 3 June 2025.
- More information
-
For more information visit https://parks.desi.qld.gov.au/parks/capricornia-cays/about/camping-booking-seasons
Capricornia Cay National Park has camping areas on North West, Lady Musgrave and Mast Head Islands that are open for seasonal camping. All Capricornia Cay National Park camping areas are extremely popular especially during peak periods and school holidays.
The Queensland National Park Booking Service has changed to a new platform for camping permits. To improve the visitor experience for making camping bookings in this new system, QPWS is making changes to the way the Capricornia Cays National Park camping areas can be booked. This means that bookings will not be able to be made 12 months in advance.
Standard annual seasonal closure periods for all Capricornia Cay Island camping areas will remain the same.
-
Eurimbula National Park -Track maintenance - Middle Creek campground 19-26 May 2025
- Location
- Eurimbula National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting road maintenance on Middle Creek Road in Eurimbula National Park.
- Commencing
- Monday 19 May 2025
- Completion
- Monday 26 May 2025
- More information
-
As a result, the following facilities will be closed for the duration of the maintenance program.
- Middle Creek campground and toilet facilities
- Middle Creek boat ramp
- Middle Creek Road from the junction of Eurimbula Creek Road to the campground
Alternative toilet and boat ramp facilities can be found at Eurimbula campground.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers, and directions from rangers and do not enter closed areas.
Facilities will reopen when conditions are considered safe.
-
Kroombit Tops National Park (KTNP) Park CLOSED for Pest Managment activities: 22/04/2025 - 20/06/2025
- Location
- Kroombit Tops National Park
- Description of Works
-
The Queensland Parks and Wildlife Service will be conducting pest activity control activities throughout Kroombit Tops National Park (KTNP), commencing 22nd April 2025, extending through to the 16th of May 2025.
QPWS will then be deploying 1080 baits across Kroombit Tops National Park as part of an ongoing Pest management program. - Commencing
- 22/04/2025
- Completion
- 20/06/2025
- More information
-
The pest activities to be carried out across KTNP is to reduce the degradation on habitat and maximise the chances of long-term recovery of populations of identified threatened species endemic to the area and associated vegetation groups. This includes the Kroombit Tops Tinkerfrog, Kroombit Tops Tree Frog, Silver headed Antechinus and Monteiths spiny crayfish.
The control activities include a focus on public safety and visitor experience within KTNP.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
The park will reopen when conditions are considered safe.
-
QLD Government Planned construction works - closure to visitor facilities
- Location
- Joseph Banks Conservation Park
- Description of Works
-
This is a Queensland Government Department of the Environment, Tourism, Science and Innovation project.
Joseph Banks Conservation Park will be undergoing construction and maintenance as part of an interpretive capital works project working with Traditional Owners groups Gooreng Gooreng, Gurang, Taribelang Bunda and Bailai. - Commencing
- end of March 2025
- Completion
- November 2025
- More information
-
Throughout this period, the following areas will be closed to the public:
- the headland carpark at the end of Sir Raphael Cilento Drive
- the Round Hill headland tracks
- the Wave and Bustard Bay lookouts
- the Round Hill Creek track section from Endevour St junction to the headland carpark
The following areas will remain open to the public:- Maritime memorial walk and carpark
- The Round Hill Creek track from the Cook Monument to Endeavour St junction
The Queensland Government thanks you for your patience while they improve the park facilities for you and other park visitors.Facilities will reopen when construction is completed.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
This alert applies to the following park:
Please visit the QLD Government Parks and Forests website for more information.
-
Reedy Creek Paperbark Forest Walk - Temporary closure
- Location
- Reedy Creek Reserver, Agnes Water
- Description of Works
- Bush Heritage Australia has temporarily closed the Paperbark Forest Walk will be closed to public access from Friday, November 24 until further notice.
- Commencing
- Friday, 24 November 2023
- More information
-
Bush Heritage Australia are working on solutions around parking issues and the impacts visitation has on this fragile environment.
-
Temporary Small Dogs and Puppies Area in Webb Park, Gladstone
- Location
- Small Dogs and Puppies Area in Webb Park, Gladstone
- Description of Works
- Council has temporarily closed the Small Dogs and Puppies area in Webb Park (a dog off-leash park) on Palm Drive as we undertake maintenance work to rectify dangerous ground conditions.
- Commencing
- Friday 11 April 2025
- Completion
- June 2025
- More information
-
A temporary small dog park has been created within the larger dog park to provide a safe space for those who need one. It is accessible through the main gate and turn to the right, and through the new gate. The bigger dogs can continue straight through to the other park.
We appreciate your patience and cooperation while works are undertaken.
If you have any questions about these works, please contact Council on 4970 0700.
-
Turtle Street Campground Closed
- Location
- Curtis Island National Park and Conservation Park
- Description of Works
- Turtle Street campground is closed due to high tides and beach erosion following the recent weather events. High tides and wave action have undermined beach access ramps, therefore campground is closed until repairs are carried out.
- Commencing
- 2 May 2025
- Completion
- 2 June 2025
- More information
-
Alternative camping is available at Joey Lees campground.
Please monitor park alerts on the department's website for updated information.
Facilities will reopen when conditions are considered safe.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
This alert applies to the following park:
-
Turtleway Bridges - Replacement
- Location
- Stirling Park, Boyne Island and Canoe Point, Tannum Sands
- Description of Works
-
Work is scheduled for replacement of two Turtleway pedestrian bridges as part of our Capital Works program.
Removal of the existing structures and installation of new Turtleway footbridges will reduce ongoing maintenance costs and improve longevity of these valuable community assets. - Commencing
- Monday 10 February 2025
- Completion
- 30 June 2025
- More information
-
Stirling Park, Boyne Island footbridge: Works have been completed and the pedestrian footbridge has reopened to public use.
Canoe Point, Tannum Sands footbridge: Works in progress. No pedestrian access. Detours around the works area required.
To keep our community safe, full closure of the Canoe Point footbridge is in place, with no pedestrian bridge access until about the end of June 2025. A pedestrian detour around the work area is required.
Replacement of these footbridges involves installation of new structures to provide improved community connectivity for years to come.
Council appreciates the patience and understanding of the community during these necessary pedestrian bridge replacement projects.
Planned works forecast, weather permitting
- OPEN: Stirling Park, Boyne Island footbridge
- Works are complete and the new pedestrian bridge is open to the public.
- CLOSED: Mon 7 Apr to Mon 30 Jun: Canoe Point, Tannum Sands footbridge
- Bridge removal works are progressing.
Bridge replacement works have involved:
- Mobilisation to site
- Create new access to site
- Removal of existing bridge, abutments and footings
- Site survey existing bridge line
- Installation of screw piles with concrete caps
- Survey footings and abutments
- Installation of new abutments with footing inspection
- Concrete curing time
- Bridge installation
- Demobilisation from site
What to expect
While Canoe Point footbridge works continue, please be mindful of construction works occurring:
- Noise and vibration from the work area is expected.
- Temporary fencing installed.
- Heavy machinery operating.
- Please follow directions and signage in the area.
- Pedestrians are required to plan an alternative route to avoid the works area near the Canoe Point footbridge.
The Turtleway Bridges Replacement project is proudly funded by the Federal Government’s Local Roads and Community Infrastructure (LRCI) Program - Phase 4.
- OPEN: Stirling Park, Boyne Island footbridge
-
Vehicle access restrictions, Joey Lees beach, Curtis Island
- Location
- Curtis Island National Park and Conservation Park
- Description of Works
-
Vehicle access to the Joey Lees beach and lower sections of the headland is no longer permitted.
This closure is necessary to enable rehabilitation of eroded sections of the Joey Lees headland to protect the natural values of the coastal headland communities. - Commencing
- 1 June 2024
- Completion
- 31 May 2025
- More information
-
It is hoped that through the completion of the rehabilitation works the natural integrity of the headland will be reinstated and continue to enhance natural visitor experiences.
A new three-bay car park has been provided on the top of the headland for day visitors. Existing pedestrian access to the beach and lower sections of the headland are maintained.
Please monitor park alerts on the department's website for updated information.
This alert applies to the following park:
-
QPWS Planned Burn Castle Tower National Park - 22 April - 31 August 2025
- Location
- Castle Tower National Park
- Description of Works
- The Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Castle Tower National Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Castle Tower NP. Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn Eurimbula National Park - 22 April - 31 August 2025
- Location
- Eurimbula National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Eurimbula National Park from 22 of April 2025 - August 31 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Eurimbula NP, including campgrounds and day-use areas, and within the townships of Agnes Water, Captain Creek and Turkey Beach.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn for Kroombit Tops National Park - 5 May to 30 June 2025
- Location
- Kroombit Tops National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting a planned burns (weather permitting) from 5th May 2025 to 30th June 2025, as part of the fire management program for Kroombit Tops National Park.
- Commencing
- 5 May 2025
- Completion
- 30 June 2025
- More information
-
Firefighters and machinery may be working along roadsides in the vicinity of Tableland Rd and the Razorback Track. For your safety and the safety of firefighters, please slow down and observe all directions and signs.
Please note: Kroombit Tops National Park is currently fully closed until the 17th May 2025 due to pest control activities, which may be running concurrently with the plan burn program.
During the planned burns, these areas may be temporarily closed to public access outside of the current full park closure:
- Tableland Road
- Razorback Track
Smoke may be seen in the vicinity of Tableland Road & The Razorback Track. Persons with respiratory or other health problems should seek medical advice on mitigating the effects of smoke inhalation.
Refunds can be applied for via your online account at qld.gov.au/camping.
Please monitor park alerts on the department's website for updated information.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Facilities will reopen when conditions are considered safe.
This alert applies to the following park:
-
QPWS Planned Burn Deepwater National Park - 22 April - 31 August 2025
- Location
- Deepwater National Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Deepwater National Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Deepwater NP, including campgrounds and day-use areas, and within the townships of Agnes Water and Deepwater.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
-
QPWS Planned Burn in Joseph Banks Conservation Park - 22 April - 31 August 2025
- Location
- Joseph Banks Conservation Park
- Description of Works
- Queensland Parks and Wildlife Service (QPWS) will be conducting planned burns within Joseph Banks Conservation Park from 22 of April 2025 – August 31st 2025, weather permitting, as part of the annual hazard reduction/conservation management program for parks and forests.
- Commencing
- 22 April 2025
- Completion
- 31 August 2025
- More information
-
These burns aim to reduce the volume of forest fuels and to create a mosaic pattern of burnt and unburnt areas. This will help reduce the intensity of any subsequent wildfires and provide favourable conditions for natural forest regeneration.
As a result, smoke may be seen in the vicinity of Joseph Banks Conservation Park, including lookouts and walking tracks, and within Seventeen Seventy.
Smoke can decrease visibility on the roads, so it is important that motorists drive safely to the conditions. Visitors and residents should close windows and doors and keep medications close by if suffering from a respiratory illness.
For more information, please call QPWS Agnes Water office on 0429 633 770.
Please observe all signage, barriers and directions from rangers and do not enter closed areas.
Stay up-to-date with Current bushfire warnings and incidents from Queensland Fire Department (QFD).
# | Name | Size |
---|
Archived public notices
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
# | Name | Size |
---|
Roadworks, conditions and closures
Refer to the RegionWatch website for up to date road conditions and scheduled works. Information and updates are posted on our Facebook page for short term and unscheduled works.
Regular maintenance and operational development of Gladstone Region roads are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
-
Refer to RegionWatch for current road conditions
-
End of Parksville Drive to Kahler Close - New Footpath
- Location
- Parksville Drive to Kahler Close, Kirkwood
- Description of Works
-
Work to construct a new footpath connecting the end of Parksville Drive to Kahler Close, Kirkwood is anticipated to start in about July.
This project will involve construction of about 80m of new pathway and is included in Council’s 2024/25 Capital Works program.
In the lead up to footpath construction, surveys have been underway in the area and site preparations will start soon. - Commencing
- 1 July 2025
- Completion
- 31 August 2025
-
The new pathway will connect to existing footpath in the area, provide greater pedestrian connectivity for the community and improve pedestrian safety to the Kirkwood shopping centre.
This project supports Council’s Pedestrian and Cycle Strategy, providing cyclists and pedestrians with a safe and dedicated pathway, reducing the need to share the roadway with motorists.
Planned Works
Site preparation works will start soon.- Two trees on the footpath alignment have been condition assessed and identified for removal in coming weeks.
- Council takes a sensitive approach to remove trees only where absolutely necessary to enable works and to ensure the safety of workers and community.
- More trees will be planted as part of landscape works towards completion of footpath construction.
- Overall path construction works: Anticipated to start from about July for about six weeks, weather permitting.
- In March: Targeted tree removal, electrical works including installation of electrical conduit, light pole footings.
- From about July: Construction of new footpath, installation of kerb ramps, bollards, signage.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
To keep our community safe and to minimise disruptions:- Work will occur in stages, commencing with tree removal in the next two weeks followed by the electrical works, weather permitting.
- Works will take place Monday to Friday, 6am-6pm.
- Machinery noise, vibration and dust can be expected from the project site.
- At times, some pedestrian and traffic disruptions.
- Please follow signs and directions.
The end of Parksville Drive to Kahler Close Construct Shared Path project is proudly supported by the Queensland Government’s Cycle Network Local Government Grants Program and Gladstone Regional Council.
-
Jeffery Court - Road Safety Improvements
- Location
- Jeffery Court, Agnes Water
- Description of Works
-
Council is undertaking road safety improvement work along a section of Jeffery Court adjacent to Tom Jeffery Memorial Park, Agnes Water.
Following community feedback and review of this busy traffic area, consideration has been given to public safety, speed limit and improvements to traffic flow to increase safety for our community and visitors to the region.
Work will be completed in stages as part of Council’s 2024/25 Capital Works program to complement later construction of the nearby Agnes Water Beach Visitor Carpark. - Commencing
- 21 October 2024 (Stage 1). Further work dates for Stage 1 completion and Stage 2 works to be advised.
- Completion
- Dates to be advised.
-
Project update
- Majority of Stage 1 roadworks are complete with a portion of remaining works to be delivered.
Work is scheduled, site conditions and weather permitting, along the northern side of Jeffery Court (on the road and embankment near the boundary of NRMA Agnes Water Holiday Park and Tom Jeffery Memorial Park):
- Stage 1 - Drainage, road widening, new kerb, asphalt reseal, line-marking and road sign installation within the work area. Installation of mountable kerbing.
- Stage 2 - Construction of retaining wall and boardwalk on embankment adjacent to Tom Jeffery Memorial Park.
More information
To make it safer for drivers, pedestrians, community and visitors to the park and beach, when complete, works along this section of Jeffery Court will introduce:
- Reverse angle parking: 18 parking bays to replace existing parallel parking bays, utilising available space and providing greater off-road safety during vehicle unpacking/loading.
- Lower speed limit: a 10km/hr shared zone will apply.
- No queue signage: traffic will not be permitted to queue on the road.
- Existing one-way traffic flow to remain: current one-way flow of traffic conditions will continue.
- Retaining wall and boardwalk: Work in 2025 to provide a safe pedestrian path to connect to existing pathways.
What to expect during works
During works, you’ll notice workers and activity in the work area with some brief traffic disruption and partial road closure required at times.- Works - Monday to Friday, 7am-5pm, site conditions and weather permitting.
- Traffic management.
- At times, dust and machinery/equipment noise can be expected from the project site.
- Some local traffic only restrictions under traffic control.
- Reduced speed limit.
- At times, partial road closure and road changes.
- Please follow signs and directions.
-
Lowmead Road - Upgrade Work
- Location
- Staged works along Lowmead Road from the Fingerboard Rd-Lowmead Rd intersection to the town of Lowmead
- Description of Works
-
The Lowmead Road Safety and Sealing Upgrade project consists of four stages of road upgrades forecast to be completed on Lowmead Road during this financial year and the next.
Sections of road will be upgraded from the Fingerboard Road-Lowmead Road intersection to the town of Lowmead.
This project will provide an improved, more resilient road with alignment adjustments to offer increased safety for motorists and improved road resilience during wet weather. - Commencing
- 7 August 2023
- Completion
- Financial year 2024/25
-
What’s been happening?
ROAD CUT AT GRANITE CREEK BRIDGE - CLOSED TO ALL TRAFFIC - UNTIL FURTHER NOTICE
UPDATE @ 22 APRIL 2025
- Following significant rainfall and water inundation in the area, Lowmead Road remains cut at the Granite Creek crossing with a full closure in place to all traffic.
- Site inspections and damage assessments at the site are continuing.
- Road closed barriers are in place with the causeway closed to all traffic. Local access is not permitted.
- The working area that has been developed in Granite Creek to support bridge construction is an active worksite. Public access is not permitted. Please observe all construction signage and barriers that are in place to protect our community from construction site hazards.
- While the road remains closed to all traffic, a diversion around the area is needed. Please continue to drive safely, to conditions, and plan extra time for travel.
- Early inspections indicate that to rebuild the causeway road to a limited condition, capable of withstanding one-way traffic, substantial civil works and time would be required.
- The normal creek flows are too high, and the banks are too steep, to allow for any local access/side track to be considered.
- Our officers are working diligently, various options are currently being outworked and a number of our teams are focussed on delivering the best possible outcome for the community.
- We appreciate your patience and understanding while we work to determine the next steps for our road network in this area.
- Granite Creek Bridge
- Bridge construction works, including minor road adjustments to align road approaches with the new bridge.
- Stages 2, 3 and 4 of Lowmead Road
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
- Local road users will have noticed approximately 2000m of sealing works completed in Stage #3, in a stretch of road between Colosseum Creek and Granite Creek.
Planned works, site conditions and weather permitting:
- Stage #2
- Stage #2 is approximately a 7km of section of road that commences at Colosseum Creek crossing and continues towards Lowmead. Construction works commenced in August 2024 and are anticipated to be completed during May 2025. This excludes the Gin Creek crossing works, anticipated to occur in July-August.
- While project works are underway, Lowmead Road is open to local traffic only, specifically for access to homes and properties. All residents who must use the road are asked to slow down, drive to conditions, observe warning signs and reduced speed zones.
- Stage #3, Stage #4
- Council has a Contractor team working on these sections of road, which are separated by Granite Creek. The Contractor team is also completing the Granite Creek Bridge works.
- Lowmead Road sustained significant damage during a flood event in early March 2025 and is currently closed to the public. The Contractor has established a temporary track for construction purposes only. There is no road access available to the public through Granite Creek.
- Road conditions to expect
- Suburb: Lowmead Road to Mount Tom
- Street: Lowmead Road from Clarkes Road to Fingerboard Road
- What’s happening:
- Road works. Closed. Local traffic only.
- Detour for non-local traffic via Gorge Road, Lowmead Road or Tablelands Road, Berajondo.
- Expect delays. Follow signs and directions.
More information
- All forecast works in 2025 will occur either on or directly adjacent to the existing road. Traffic controls will be in place, so please observe directions and reduced speed zones at all times.
- Local road users should anticipate significant site activity while multiple crews (both Council and Contractors) will be working simultaneously across Stages 2, 3 and 4 and the Granite Creek Bridge site.
- Noise, dust, construction traffic and heavy machinery is expected in the area.
The Lowmead Road Safety and Sealing Upgrade project is being delivered by Council and its Contractors in 2024 and is included in Council’s Capital Works program. This project has secured the support of the Federal Government to widen and seal more than 20km of Lowmead Road in 2024 via the Remote Roads Upgrade Pilot Program (RRUPP). The Granite Creek Bridge project has secured funding from Disaster Recovery Funding Arrangements (DRFA), which joins Commonwealth and State government funding to help communities recover from disasters.
-
Matthew Flinders (Marina) Bridge on Bryan Jordan Drive closure for essential maintenance
- Location
- Matthew Flinders (Marina) Bridge
- Description of Works
- Council wishes to advise that the Matthew Flinders (Marina) Bridge on Bryan Jordan Drive will be closed for routine scheduled maintenance.
- Commencing
- 6.30am Tuesday 27 May 2025
- Completion
- 4pm Tuesday 27 May 2025
-
During this period, the bridge will be closed to all vehicles and unavailable for watercraft requiring a bridge lift.
While under traffic management, detours will be in place for all vehicular traffic, and an alternative route will need to be used via Hanson Road & Alf O’Rourke Drive.
We appreciate your patience and understanding while these essential works are carried out.
Please contact Water Mechanical-Electrical Team on 4970 0700 regarding any issues or concerns.
-
Oyster Creek, Round Hill Rd - Roadworks
- Location
- Oyster Creek, Round Hill Road
- Description of Works
-
These works are included in Council’s 2024/25 Capital Works program and will involve widening, sealing, road stabilisation and construction of guardrail/safety barriers across Oyster Creek.
The work zone is 400m either side of Oyster Creek, Round Hill Road, in vicinity of Murphy Road.
There will be traffic disruptions with at times, delays of up to 10 mins experienced to enable road sealing and road stabilisation activities.
To minimise disruptions, where practical, necessary delays during works will be planned with consideration of peak travel times for work and school. - Commencing
- 19 May 2025
- Completion
- 31 August 2025
-
PLANNED WORKS FORECAST
Works are anticipated to occur in the period from 19 May to end August, site conditions and weather permitting.- Road widening, stabilisation and sealing 400m either side of Oyster Creek.
- Installation of concrete batter protection and guardrails.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
WHAT TO EXPECT
Please be mindful of construction works occurring:
- Work will be carried out Monday to Sunday from 6am to 6pm.
- Noise, vibration and dust from the work area is expected.
- Heavy machinery and equipment operating.
- Traffic disruptions and traffic management with at times, delays of up to 10 mins.
- Reduced speed limit.
- Please plan for delays, drive to conditions and follow directions and signage in the area.
The Oyster Creek, Round Hill Road safety improvement works are proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.
-
Rocky Crossing Road - Roadworks
- Location
- Rocky Crossing Road, Round Hill
- Description of Works
- These works are included in Council’s 2024/25 Capital Works program and will involve widening, rehabilitation of the road and resealing. All works will occur on the current road alignment.
- Commencing
- Mid-March 2025
- Completion
- 31 July 2025
-
Planned Works
Works are anticipated to occur from mid-March to July, site conditions and weather permitting.Works from mid-March to July, site conditions and weather permitting.
- Residents and business owners in the area car expect traffic control to be established on-site.
- Access will be maintained, with some brief interruptions to driveway access.
- Impacted residents and business owners can anticipate direct contact from Council construction personnel before any works that will affect current driveways.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
Please be mindful of construction works occurring:
- Work will be carried out Monday to Friday from 6.30am to 4.30pm.
- Noise, vibration and dust from the work area is expected.
- Heavy machinery and equipment operating. Machines and equipment will be used to remove the current road surface, rehabilitate the road and to reseal the surface.
- Traffic management at times, including traffic disruptions and possible access/exit restrictions.
- Pedestrian access restrictions.
- Please follow directions and signage in the area.
The Rocky Crossing Road, Round Hill project is proudly funded by the Australian Government’s Roads to Recovery 2024-25 program.
-
Turkey Beach Road Upgrades
- Location
- Turkey Beach Road, Turkey Beach
- Description of Works
-
Road realignment upgrade and safety improvement works including road widening and road resealing.
Works Area #1 - Between Dyckhoffs Road and Scrubby Creek
Works Area #2 - Between Scrubby Creek and Sandy Creek
During construction works please plan for possible delays, speed reductions and traffic control measures.
Traffic reduced to single lane, as required.
Motorists are urged to drive carefully through the works area and adhere to any reduced speed limits, changed traffic conditions or directions. - Commencing
- Late May 2024
- Completion
- Mid 2025
-
Turkey Beach Road Safety Improvement works are proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.
Water & Sewer interruptions
Refer to the RegionWatch website for up to date interruptions and scheduled works.
Regular maintenance and operational development of Gladstone Region water and sewer networks are conducted by Council staff throughout the year.
For more information, please contact Council on (07) 4970 0700.
After water is turned on:
- On resumption of the water supply a hot water tap should be turned on to flush any air pockets from the pipes, then turn the hot water heater on again.
- We advise that you check the water prior to use. If it appears discoloured we suggest you turn on the nearest external tap to the meter and let it run for a period of time, or until it runs clear, and then do the same to the furthest external tap from the meter, to clear your pipework.
- Please do not wash clothes at this time to prevent staining from any discoloured water.
Council apologises for any inconvenience this interruption may cause. For more information contact us online or call on (07) 4970 0700.
-
Calliope Sewer Pump Station Works
- Location
- Monterey Way, Calliope
- Description of Works
- Works will be undertaken to upgrade the current chemical dosing unit on site to improve corrosion control and reduce sewer odour.
- Commencing
- 13 May 2025
- Completion
- Mid-July 2025
- More information
-
Civil and electrical works will be required to replace the existing temporary unit and install a permanent chemical dosing unit.
This project aims to provide improved infrastructure, reducing the need for on-going maintenance while reducing the risk of unplanned sewer disruptions for residents.
These works are included in Council’s Capital Works program.
Above dates are a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
- Works from Monday to Friday, 7am-4.30pm, weather permitting.
- Machinery operating.
- Concrete slab demolition, removal and construction.
- Noise, vibration, odour and dust can be expected from the project site.
- At times, some additional traffic in the area and pedestrian disruptions.
- No interruption to sewer services is expected.
If near the area, please be mindful of works and follow signs and directions.
-
Sewer Main Renewal
- Location
- Several locations across Gladstone, Boyne Island, Tannum Sands and Calliope
- Description of Works
-
Sewer main renewal works will occur in stages in various locations across the region.
Works are part of a multi-year Capital Works project to renew sewer main assets in areas of Boyne Island, Calliope, Gladstone and Tannum Sands to improve network reliability, operational efficiency and reduce ongoing maintenance costs. - Commencing
- Monday 28 April 2025 (Stage 1)
- Completion
- Friday 10 October 2025 (Stage 1)
- More information
-
This project will involve sewer cleaning, relining and junction sealing.
Sewer services are not expected to be affected by these renewal works however this method of pipeline rehabilitation may produce minor noise disturbances, additional traffic, and possibly odour for short periods.
Access to properties will only be required when entry is necessary to access Council’s sewer main assets, complete the works, or for service junction repair and connection to the new sewer pipe. Entry to properties will be made in accordance with Part 2, Section 144 of Local Government Act 2009.
Planned Works, weather permitting
- 12 May to 24 June: Sewer cleaning works
- 16 June to 10 October: Relining works
- Program of works information will be provided here when finalised.
Above dates are a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.What to expect
- Works between 6.30am to 6.30pm, Monday to Friday and 6.30am to 5pm on Saturday, weather permitting.
- Council Contractors will carry identification.
- Access if required only to external areas of property, including backyards.
- Please ensure clear access to any sewer main access points on your property.
Residents will receive further access notification from the Contractor closer to works. Please relocate/restrain any animals and enable access through any gates during this timeframe.
-
Unplanned Maintenance - Agnes Water Waste Water Treatment Plant
- Location
- Agnes Water
- Description of Works
- Due to maintenance work at the Trade Waste/Septage receival station at Agnes Water WWTP. All liquid waste disposal at this location is directed to Gladstone Waste Water Treatment Plant, 17 Albert Road, Callemondah.
- Commencing
- Friday 26 July, 2024
-
Half-Yearly Water Meter Readings - Commencing 17 June 2025
- Description of Works
- Council would like to advise residents that half-yearly water meter readings will commence from Tuesday 17 June 2025.
- Commencing
- Tuesday 17 June 2025
- Completion
- mid-July 2025
- More information
-
Council Officers conducting readings will be dressed in GRC-branded clothing and will carry an authorised officer card featuring photographic identification.
Residents are asked to keep water meters accessible and clear of building materials, soil, vehicles, or other objects.
Council also reminds residents to keep unrestrained dogs controlled and gates closed.
Water consumption for this half-year period will be billed in the annual rates and charges notice to be issued in August 2025.
Residents unable to locate their water meter can phone Council on 4970 0700.
More information
-
Sewer Manhole Renewal
- Location
- Various areas in Calliope, Boyne Island and Gladstone
- Description of Works
-
Sewer Manhole Renewal work is being delivered in stages across Gladstone and involves rehabilitation works to improve reliability of the sewer network, reduce ongoing maintenance costs and meet wastewater sustainability objectives.
Machinery operation, vehicle movements, odour and noise will be associated with this work. Sewer services are not expected to be affected. - Commencing
- Monday 28 April 2025
- Completion
- Friday 27 June 2025
- More information
-
Several assets have been identified as requiring upgrade or repair to prevent water infiltration into the sewer network.
Works are part of Council’s continuous focus on infrastructure improvements and will involve relining or refurbishment works of sewer manholes in areas of Calliope, Boyne Island and Gladstone.
This project follows routine inspection of sewer manholes throughout the region and the development of a prioritised works program.
Access to properties will only be required when entry is necessary to access Council’s sewer main assets, complete the works, or for service junction repair and connection to the new sewer pipe. Entry to properties will be made in accordance with Part 2, Section 144 of Local Government Act 2009.
Planned Works, weather permitting
- Gladstone (along Chapple St, Toolooa St, Leo Zussino Dr and Kirkwood Rd)
- Boyne Island (along Bluewater Dr and Jacaranda Dr)
- Calliope (along Dawson Highway and Sun Court)
Above dates are a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
- Works between 6.30am to 6.30pm, Monday to Friday and 6.30am to 5pm on Saturday, weather permitting. Some night works may be required if determined by operational requirements.
- Council Contractors will carry identification.
- Access if required only to external areas of property, including backyards.
- Please ensure clear access to any sewer main access points on your property.
Residents will receive further access notification from the Contractor closer to works. Please relocate/restrain any animals and enable access through any gates during this timeframe.
-
Seventeen Seventy Sewer Rising Main Replacement
- Location
- Captain Cook Drive, Seventeen Seventy
- Description of Works
-
Works to relocate and replace 1000m of existing sewer rising main along the coastline adjacent to Captain Cook Drive at Seventeen Seventy will occur from early December 2024 to June 2025, site conditions and weather permitting.
Works will start near Endeavour Park and finish near the Seventeen Seventy boat ramp.
New alignment of the sewer rising main will prevent risks of uncontrolled sewer release to the immediate environment, supporting objectives of Council’s Our Coast Our Future Coastal Hazard Adaption Strategy to ensure appropriate adaptation responses to help avoid, mitigate, and manage the risk of coastal hazards.
This project is included in Council’s Capital Works program. - Commencing
- Late November 2024
- Completion
- June 2025
- More information
-
Work will generally involve:
- Removal and/or grouting capping of existing redundant sewer rising main (located within the foreshore area),
- Installation of new sewer rising main within the road reserve,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
Planned works forecast, site conditions and weather permitting
Works along Captain Cook Drive, near the marina to the 1770 caravan park carpark, within the project work area.
- Traffic disruptions including diversions.
- During works, on-site traffic control will be in place.
- Machinery noise during works.
- Access remains open to businesses and park areas.
- Road-side parking disruptions.
- Some pedestrian disruptions.
- Please follow signs and directions.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
What to expect
Work is being planned in stages with public safety as a priority and with consideration of peak holiday times, the community and visitors to our region.
When works are underway in 2025:
- Contractors in the area on weekdays with at times, work at night and on weekends.
- Equipment and machinery operating with noise and dust likely from the project area.
- At times, some pedestrian detours, disruption to traffic flow, single lane alternating traffic and parking restrictions within the work area.
- At times, some amenities near the immediate work area will be closed for public safety.
- Please follow signs and directions and plan for road and pedestrian changes near the works area.
The Seventeen Seventy Sewer Rising Main Replacement project is funded by the Queensland Government’s QCoast2100 program and Gladstone Regional Council.
-
Tannum Sands Sewer Rising Main Replacement
- Location
- Millennium Esplanade, Tannum Sands from the northern end to just south of the Surf Lifesaving Club
- Description of Works
-
Works to upgrade the sewer rising main will occur until June 2025, site conditions and weather permitting.
The existing 370m long sewer rising main pipeline, constructed in 1976, is located along the eastern side of Millennium Esplanade, Tannum Sands.
This asset has been condition assessed and identified as being at the end of its service-life and needing replacement. This project is included in Council’s 2024/25 Capital Works program with work to be carried out by a Contractor.
- Commencing
- Late January 2025
- Completion
- June 2025
- More information
-
Work will involve:
- Removal and/or grouting of existing redundant sewer rising main (located under road and footpaths in some areas),
- Installation of new sewer rising main,
- New sewer rising main connection to the existing network,
- Testing and commissioning of the new sewer rising main.
What to expect- Equipment and machinery operating in the area, noise and dust likely from the project area.
- A temporary on-site work area has been established at the northern end of Millennium Esplanade.
- At times, some pedestrian detours, disruption to traffic flow, and parking restrictions will be experienced along the esplanade.
- Work is planned to occur in stages to help minimise public disruptions.
- To keep the public safe, there may be times when some amenities near the immediate work area may also need to be closed.
Planned worksProject works are continuing along Millennium Esplanade.
- Through traffic restored from Beach Avenue towards the Tannum Sands Surf Life Saving Club.
- Works underway to return site to open on Friday 2 May.
- End of May completion: Project completion due end of May.
-
Advanced Water Meters - Stage 3 Installation
- Location
- Clinton, Calliope, Mount Larcom and parts of Kirkwood
- Description of Works
-
Upgrade of existing water meter infrastructure to new, advanced water meter infrastructure at residential and commercial properties in Clinton, Calliope, Mount Larcom and parts of Kirkwood.
These works are Stage 3 of a whole-of-region, multi-year Capital Works project to upgrade existing water meter infrastructure to new, advanced water meter infrastructure. - Commencing
- February 2025
- Completion
- 30 June 2025
- More information
-
The installation of advanced water meters and access to associated technology will provide significant benefits to residential households and businesses by:
- Enabling early detection of leaks.
- Providing data and information online so the user can review and manage their water usage.
- Enabling Council officers to respond more effectively to usage enquiries regarding connections.
Every property in Clinton, Calliope, Mount Larcom and some properties within Kirkwood with an existing water meter will have upgraded infrastructure installed between February and June 2025, between 7am and 5pm Monday to Friday, with weekend work (involving later start times) approved by Council.
The age of a property’s existing water meter will determine if it is fully replaced as part of the upgrade, or if the existing asset can be retained and an advanced water meter infrastructure sensor added. There is no cost to property owners associated with this upgrade.
What to expect during works
- Council Contractors, Taggle Systems, will carry identification with them.
- Water meter upgrade takes about 15 minutes depending on the complexity of your meter.
- A vacuum truck may be required at some sites. If this is the case, please expect some noise.
- Water will be disconnected during works, stopping water flow for the installation period.
- If water is flowing through the meter and we are unable to make contact, we will come back at a later stage.
- A calling card will be left in your letterbox/on your property to advise if the installation was complete or if you need to contact Council to arrange a time for installation completion.
If you have animals or locked gates and need to be present at the install, or if you have any questions about this project, please contact Council on 4970 0700 or visit your local Council office at Mount Larcom, Calliope or Gladstone.
Following installation, residents can sign up to the My Water portal which will show near real-time water usage. Users can set up high usage alerts and receive monthly water usage reports by email.
Living Here
- Pets and Animals
- Residents
- Report
- Environment
- BackEnvironment
- Air Quality
- Biodiversity
- Biosecurity
- Blue-green algae blooms
- Bushfire Mitigation
- Coasts and Coastal Vegetation
- CoastSnap
- Conservation Programs and Initiatives
- Erosion and Sediment Control
- Feral Animals
- First Nations Fire and Land Officer
- Landfill Gas Abatement
- Mosquitoes
- Pests and Weeds
- Weed Spray Equipment Hire
- Wildlife
- Community Development
- Community Investment
- Services
- Emergencies

Latest CONNECT News out now
More Information
The cookbook is a collaborative effort between Gladstone Regional Council and Gladstone Region Neighbourhood Centre, proudly presented as part of Welcoming Week celebrations.
Download the cookbookGladstone Regional Council
Connect. Innovate. Diversify.
Get in Touch
Phone
(07) 4970 0700
Opening Hours
8.30am - 5pm Monday to Friday
Social media
Postal Address
PO Box 29, Gladstone Qld 4680
Council Offices
101 Goondoon Street, Gladstone Qld 4680
3 Don Cameron Drive, Calliope Qld 4680
41 Blomfield Street, Miriam Vale Qld 4677
Cnr Wyndham & Hayes Avenues, Boyne Island Qld 4680
Rural Transaction Centres
71 Springs Road, Agnes Water Qld 4677
47 Raglan Street, Mount Larcom Qld 4695
Footer Acknowledgement
Gladstone Regional Council would like to acknowledge the Bailai, the Gurang, the Gooreng Gooreng and the Taribelang Bunda people who are the traditional custodians of this land. Gladstone Regional Council would also like to pay respect to Elders both past, present and emerging, and extend that respect to other Aboriginal and Torres Strait Islander people. Learn more about Council's Reconciliation Action Plan (RAP).
Chat Popup
All content © Gladstone Regional Council. All Rights Reserved.
Back to the top