- Location
- Oyster Creek, Round Hill Road
- Description of Works
-
These works are included in Council’s 2024/25 Capital Works program and will involve widening, sealing, road stabilisation and construction of guardrail/safety barriers across Oyster Creek.
The work zone is 400m either side of Oyster Creek, Round Hill Road, in vicinity of Murphy Road. - Commencing
- 19 May 2025
- Completion
- 12 September 2025
-
PLANNED WORKS
- Contractor is now off-site.
- Majority of works are complete. Line-marking remains and is scheduled for Friday 12 September.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
WHAT TO EXPECT
Please be mindful of activity in the area during line-marking works.
The Oyster Creek, Round Hill Road safety improvement works are proudly funded by the Queensland Government through the Transport Infrastructure Development Scheme (TIDS) and Gladstone Regional Council.