- Location
- Rocky Crossing Road, Round Hill
- Description of Works
- These works are included in Council’s 2024/25 Capital Works program and will involve widening, rehabilitation of the road and resealing. All works will occur on the current road alignment.
- Commencing
- Mid-March 2025
- Completion
- 29 August 2025
-
Planned works
- Majority of project work is complete.
- By end of August: Contractor to demobilise from site
- September: Brief return to site for second-seal layer and line-marking
During works please follow signs and directions in the area.
Please use this information as a guide only. Due to the nature of construction projects and unforeseen delays, works may vary.
The Rocky Crossing Road, Round Hill project is proudly funded by the Australian Government’s Roads to Recovery 2024-25 program.