Agnes Water Skate Park Revitalisation

  • Project typeRevitalisation
  • Project value$1.94M
  • Project scheduleConstruction from early February to late May 2026.
  • Completion Date29 May 2026
Agnes Water Skate Park - Final Concept Design2.jpg

More information

Site Investigation and Detailed Design phase commenced on 9 January 2025.

Construction started early February 2026 and is planned to continue until about late May 2026. 

Once complete, Agnes Water will have a fit-for-purpose skate facility that is safe, modern, and suits a range of skill levels for skateboards, BMX, and scooters.

What's been happening? 
  • Council takes a sensitive approach to vegetation clearing and has undertaken environmental assessments of the area.  
  • Targeted removal of vegetation including some upper storey trees and undergrowth has occurred.  
  • As part of Council's Environment Policy, in undertaking the removal of trees, a revegetation plan is currently underway for new trees to be planted within the region.  
  • Demolition and removal of the existing skate park and other infrastructure has occurred. 
  • Site preparation works are in progress. 
What to expect 
  • Works will occur Monday to Saturday, 6am-6pm with general construction activity expected at the site.  
  • The existing skate park, including playground and amenities, is closed for the duration of the works.  
  • A pedestrian detour is in place on the footpath linking the park to Agnes Water State School.  
  • Temporary fencing and screening is in place.  
  •  Please follow signs and directions if in the area. 

Project dates mentioned are a guide only. Due to the nature of construction projects and unforeseen delays, works and timeframes may vary. 

* To enable our teams to focus on project progression, for project queries, please contact Council on 4970 0700. 

 