- Location
- 60 Tank Street, Gladstone
- Description of Works
-
Works in 2021 included installation of site boundary fencing, filtration plant upgrades, Aquatic Play Park upgrades, Building Renewals included amenity upgrades and addition of a new Accessible Adult Change Room and external pool lights replacement.
Works also included Stage 1 Building Renewals, with upgrades to amenities in the 25m pool area and Stage 2 Building Renewals including upgrade to facilities and main amenities building. This included improved change rooms with two new Disability Discrimination Act (DDA) accessible facilities and three new family change rooms.
Works in 2022 have included new roof structures over main amenities, new awning to the existing kiosk and front entrance upgrade. Stage 3 Building Renewals including 25m pool upgrades, building enclosure works and upgrades to the 25m pool water heating system were completed with work then on the 50m grandstand and shade sail upgrades.
- Commencing
- August 2020, various stages
- Completion
- Various stages continuing until 2023
- More information
-
Aquatic Play Park upgrade is complete with towering dumping buckets, water cannons and two slides, offering 13 interactive features for aquatic play.
The Aquatic Play Park operates in the warmer months of the year. Check opening times and learn more about the Gladstone Aquatic Centre and other facilities in the region www.gladstone.qld.gov.au/pools-aquatic-centres
WHAT’S BEEN HAPPENING?
We’re pleased to have introduced our 50m grandstand and shade sail upgrades late last year, providing a fresh, new look to the 50m pool area, and helping to provide all-year-round comfort for our patrons.
25M POOL FILTER UNDERGROUND PIPE REPAIRS
Investigations are continuing into engineering requirements for repairs to the 25m pool filter plant’s underground pipework. Location of the pipe leaks and pipe arrangement could potentially make this work challenging. Planning is underway on how to execute these works safely and with minimal impact on infrastructure.
50M POOL RELINING DEFERRED
Works for complete replacement of pool tiles in the 50m pool, which was planned for Winter 2023 have been deferred.
A new implementation schedule for the 50m pool retiling is being determined.
The new timeframe for these works will be shared when confirmed.
Gladstone Regional Council is being assisted to deliver this improved facility for the region with:
- $2.4m State Government funding, through the 2021-24 Works for Queensland Program,
- $1.2m State Government funding, through the COVID Works for Queensland Program, and
- $1.6m through the Federal Government’s Local Roads and Community Infrastructure Program.