PROJECT Construction Value Construction Jobs - Peak Operational Jobs Gladstone area | Project Name Location (Company) | Details | Status | Government Website (Click icon to access government website data on project) | Company/Project Website (Click Icon to access company website data on project) |
APLNG $20B (Est)Construction 3,300 Operational 140 | Australia Pacific LNG Curtis Island (Origin/Conoco Phillips/Sinopec) | Integrated liquefied natural gas (LNG) project. (Joint venture between Origin Energy - 37.5%, Conoco Phillips - 37.5% and Sinopec - 25%). - Gasfields: Walloons Gasfields, stretching from Injune to Millmerran
- Pipeline: from gasfields to Gladstone
- Processing plant and export terminal: Curtis Island, near Gladstone
| 
PROJECT UNDERWAY | 
Coordinator-General |  |
GLNG $20B (Est) Construction 3,300 Operational 140 | Gladstone LNG Curtis Island (Santos/Petronas/ Total/KOGAS/) | Santos Limited - 30%, Petroliam Nasional Berhad (PETRONAS) - 27.5%, Total - 27.5% and KOGAS - 15% jointly are developing a liquefied natural gas (LNG) export facility at Gladstone in Central Queensland, Australia to commercialise their Queensland coal seam gas (CSG) resources in the Comet Ridge and Roma region. The designated proponent for the project is Santos Ltd. The project involves extraction of coal seam gas from fields around Roma, Emerald, Injune and Taroom, a 435 kilometres gas transmission pipeline from the gas fields to Gladstone, an LNG facility of approximately 10 million tones per annum on Curtis Island near Gladstone and associated infrastructure including marine facilities, port dredging and a potential access road and bridge at Gladstone. The LNG facility is proposed to be developed in three stages, the first of which will have a capacity of approximately 3-4 million tones per annum. The LNG will be exported to overseas markets. |  PROJECT UNDERWAY |  Coordinator-General |  |
QCLNG $20B (Est) Construction 3,300 Operational 140 | Queensland Curtis LNG Curtis Island (BG Group) | The Queensland Curtis LNG project proposes to develop an integrated liquefied natural gas project in Queensland comprising: - expansion of coal seam gas operations in the Surat Basin to provide gas for two liquefied natural gas plants or trains and gas for domestic markets
- development of a gas and water pipeline network of approximately 800 kilometres including:
- 220 kilometres network of gas and water pipelines connecting the primary gas fields - 200 kilometres lateral to other nearby gas resources - 380 kilometres pipeline to the liquefied natural gas plant at Gladstone - development of the liquefied natural gas processing and export facility on Curtis Island, near Gladstone, comprising:
- up to three liquefied natural gas trains of total capacity approximately 12 million tonnes per annum (a first train to be followed by a second within a year and with the potential development of the third train) - three storage tanks of up 200,000 cubic metres each (one for each liquefied natural gas train) - a marine jetty containing specialised liquefied natural gas loading facilities and berths. | 
PROJECT UNDERWAY | Coordinator- General |  |
ALNG $20B Construction 3,000 Operational 250 | Arrow LNG Curtis Island (Arrow CSG (Australia) Pty Ltd (Arrow Energy) -Royal Dutch Shell & Petrochina Company Limited) | A joint venture of Royal Dutch China - 50% and Petrochina - 50%. Integrated liquefied natural gas (LNG) project. - Processing plant and export terminal: Curtis Island
- Gas pipeline: between Gladstone City Gas Gate and Curtis Island
- LNG processing plant and export facility (four trains with a total capacity of up to 16 million tonnes per annum of LNG)
- gas pipeline
- dredging of Port Curtis
|  Supplementary EIS submitted February 2013 |  Coordinator-General |  |
ASP $1.2B | Arrow Surat Pipeline
(Surat Gladstone Pipeline Pty Ltd -Arrow Energy -Royal Dutch Shell & Petrochina Company Limited) | The proponent for the Surat to Gladstone Pipeline proposal is Surat Gladstone Pipeline Pty Ltd (SGP), a wholly owned subsidiary of Arrow Energy Ltd. Arrow Energy Ltd currently holds 90 000km2 of coal seam gas exploration tenements in the Surat Basin. The pipeline is proposed to deliver coal seam gas (CSG) from adjacent to the Kogan North Central Gas Processing Facility near Dalby to a proposed Liquefied Natural Gas (LNG) facility at Fisherman’s Landing near Gladstone (the LNG facility is subject to a separate assessment process under the Environmental Protection Act 1994). The 660mm diameter high pressure buried steel gas pipeline would be approximately 470km long. The pipeline would have a minimum technical design life of 40 years. Above ground facilities would be required at intervals along the pipeline, including: mainline valves; cathodic protection systems; and marker signs. |  Environmental Authority Issued January 2010. Pipeline Construction expected to commence in 2015/16 |  Department Environment and Resource Management |  |
ABP $480M (A$) Construction 350 Operational 10 | Arrow Bowen Pipeline
(Arrow Energy -Royal Dutch Shell & Petrochina) | The project would involve the construction of a 600 km long point-to-point transmission pipeline consisting of a main pipeline and several lateral pipelines to convey coal seam gas (CSG) from Arrow Energy’s gas fields in the Bowen Basin, located approximately 90 km north of Moranbah in central Queensland, to Gladstone for eventual export as liquefied natural gas (LNG). Construction of the proposed pipeline is anticipated to commence in 2015 with the first gas supplied to an LNG plant in Gladstone in 2017. |  Awaiting Departmental decision on supplementary EIS |  Department Environment and Resource Management | |