Parks Scheduled Works Parks Scheduled Works

Regular maintenance and operational development of Gladstone Region parks, reserves, open spaces and playgrounds is conducted by Council staff throughout the year including all furniture, play equipment, structures and trails. Below is a list of projects under way or soon to start.  Please note: Commencement and completion dates are subject to favourable weather.

For more information, please contact Council's Parks and Environment division on 07 4977 6899.

Name of Park Location Description of Works Commencing Completion
Peters Play Park Ocean Street, Tannum Sands Removal of faulty playground equipment. Community consultation is in progress regarding replacement. 28 February 2018 To be confirmed
Millennium Esplanade Millennium Esplanade, Tannum Sands Replacement of all beach shower infrastructure. Only one shower will be closed off at a time. 1 March 2018 To be confirmed
31 August 2018
Millennium Esplanade Millennium Esplanade, Tannum Sands Electrical maintenance to resolve tripping issues effecting the footpath and hut lighting. 26 March 2018 To be confirmed
31 August 2018
Beaumont Park Corner J Hicky Avenue and Aramac Drive, Clinton Blue green algae outbreak has been identified in one of the ponds. DO NOT go near the water. 22 May 2018 Being monitored
weekly. To be advised.
Byellee Wildlife Reserve Dawson Highway, Byellee Fuel reduction burn. 13 July 2018 13 July 2018
Millennium Esplanade Millennium Esplanade, Tannum Sands Construction of the BAM stage. 16 July 2018 14 September 2018
Tom Jeffery Park Jeffery Court, Agnes Water Rectification of vandalism and amenities maintenance. 16 July 2018 19 July 2018
South End,
Curtis Island
South End,
Curtis Island
Fuel reduction burn in reserve areas. 16 July 2018 13 August 2018
Lions Park, Gladstone 95 Dawson Highway, West Gladstone Drainage maintenance in Water Play cog/area. 23 July 2018 27 July 2018
Adelaide Street Median Adelaide Street, South Gladstone 30 trees removed from median. Traffic management will be in place. Work will only be undertaken 7am-3pm daily. 6 August 2018 8 August 2018